Permit: T20RW02569

Parcel: 140580010

Inspection Status: Continued

Inspection History: TDOT-EXCAV GENERAL INSPECTION

Permit Number - T20RW02569

Inspection Description - TDOT-EXCAV GENERAL INSPECTION

Inspection Status - Continued

Date Description Inspector Results Comments
09/01/2020 TDOT-EXCAV GENERAL INSPECTION Continued LAST PIECE OF SIDEWALK SUBGRADE ON CRAYCROFT IS GOOD TO POUR
CONCRETE SIDEWALK IN LITTLETOWN DRIVEWAY MEETS SPEC
08/21/2020 TDOT-EXCAV GENERAL INSPECTION Continued Observed concrete forms for ramps on Craycroft, and header curb were all in general compliance with City of Tucson specifications. Ramps will be poured next week.
08/13/2020 TDOT-EXCAV GENERAL INSPECTION Continued subgrade for sidewalk and ramps on littletown rd meet depth and compaction
08/11/2020 TDOT-EXCAV GENERAL INSPECTION Correction Required depressed curb for sidewalk on northside of driveway on craycroft needs removed an replaced. sidewalk area on littletown driveway is out of spec. they will be cutting that out and replacing with concrete
08/07/2020 TDOT-EXCAV GENERAL INSPECTION Continued sidewalk they poured yesterday is in spec. i made a field adjustment at the transition in the header curb. i moved it back to line up. they will repair a bad piece of asphalt while they have the paver onsite traffic control is ok
08/05/2020 TDOT-EXCAV GENERAL INSPECTION Continued TRAFFIC CONTROL IS OK POURING SIDEWALK WITH CURB. EXPANSION MATERIAL HAS BEEN INSTALLED, SUBGRADE FOR RAMP IS GOOD. IT HAS BEEN FORMED SEPRATLY FROM CURB RAMP WILL NOT BE POURED TODAY
07/31/2020 TDOT-EXCAV GENERAL INSPECTION Continued Inspected concrete forms for curb. Subgrade was dense, and clean. Proper depth was achieved. Concrete will be place on Monday.
07/07/2020 TDOT-EXCAV GENERAL INSPECTION Continued All concrete forms were with City of Tolerance specifications (Under 2%). ABC material was compacted with use of jumping jack, ABC was firm. Proper depth of 4" was achieved. Concrete to be poured on 7-8-2020.
06/03/2020 TDOT-EXCAV GENERAL INSPECTION Not ready for Inspection WAITING ON PLAN REVISIONS
05/26/2020 TDOT-EXCAV GENERAL INSPECTION Continued TRAFFIC CONTROL IS OK SHOULDER CLOSURE CALLED TOM WEST END OF SIDEWALK LOOKED LIKE IT WAS GOING TO BE FLOODED WHEN IT RAINED
05/26/2020 TDOT-EXCAV GENERAL INSPECTION Continued MET WITH TOM AND CONTRACTOR ABOUT SIDEWALK. CONTRACTOR WILL TALK TO ZELIN ABOUT ADDING A SCUPPER AND MAYBE A DRAINAGE SWALE TO CONTROL RUN OFF