Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 09/17/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
4032/4034 Demo completed. Gravel spread. All debri hauled off. |
| 09/15/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
4032/4034 site - Graded and ready for gravel placement. Gravel in piles on site. Removing the fence/trash located behind building area. |
| 09/15/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
All debri removed from El Molinto site. |
| 09/14/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
4032/4034 site - Sewer line located and plugged. |
| 09/09/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
No additional work performed. |
| 09/08/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
4032/4034 site - Building gone. Slab removed. Pile of concrete stock piled for removal. Need to fill in at slab area. |
| 09/03/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
4032/4034 site - all wood debri removed from site. |
| 09/02/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Demolishion started. at 4032/4034. Walk thru with contractor prior to start. Nothing found. Watched the demo on and off all day. Building down by 1 pm. |
| 09/01/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
No sign of work at 4032/4034. |
| 08/27/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
No sign of work at 4034 E. Grant Rd. |
| 08/25/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Permit reopened by downtown. No sign of work at 4034 E. Grant Rd. |
| 06/09/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
4026 E Grant Rd.- Site has final grade done. Equipment removed. |
| 05/28/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Demo site. Equipment ready for haul off. Fence taken down. Site filled. Gravel spread. |
| 05/27/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Took photos of sewer line plug and excavation where septic tank was removed. |
| 05/21/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Pulling up slabs and loading debri. Front screen wall removed. |
| 05/18/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
All floor tile removed from south west building by SHC. Loading debri and hauling off. |
| 05/14/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Walk thru 06:40 - all buildings empty. Waiting on operator. Plan is to take down the back 2 buildings today and leave front building for tomorrow. All informed that no building walls could be left standing if demo started. |
| 05/13/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Temp. fence erected. Crew working by hand to remove misc. metals. Equipment on site. |
| 05/07/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Southwest Enviro on site - Asbestos removal. |