Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 06/29/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
All work including final striping complete. Approved. |
| 06/15/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Met RP Companies to look at paving. P1 Paving will be back Thursday to complete rest of Moratorium patch. All other patches complete. Collars installed on vaults. |
| 06/02/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Will be milling and replacing 2"AC on 6/4. Will keep one lane of access to Park Tucson Garage at all times. Flaggers will be present.Patching Scott North of Congress today. South of Congress on 6/3 |
| 06/01/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Meeting on site to discuss mill and fill of Scott. Will set up meeting with Park Tucson to discuss garage access. |
| 05/19/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
CSC on site core drilling walk way. TC CHeck OK. Flagging operation at Congress/Scott. One way on Scott. Access to Garage Maintained. |
| 05/08/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Flash 1 FO Precon with RP, Zayo, Downtown Alliance, and Park Tucson. Construction to start 5/13 or 5/14. |