Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T20RW02241

Parcel: 13010161A


Addresses:

3102 E 26TH ST


Inspection Status: Re-inspection required

Inspection History: TRSP - ROW - Recurring

Permit Number - T20RW02241

Inspection Description - TRSP - ROW - Recurring

Inspection Status - Re-inspection required

Date Description Inspector Results Comments
09/15/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued- No activity
11/30/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Continued. No traffic elements in place. No activity on site
08/23/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued-No activity permit expired 8/3/21.
11/24/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
08/13/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued-No activity permit expired 8/4/21
11/23/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
08/05/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued-No activity permit expired 8/1/21
11/22/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
07/08/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued-No activity looks like a cabinet/vault was installed since last inspection.
11/20/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Set up began at 0930.
06/09/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued-No activity
11/18/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site.
05/21/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued-No activity
11/11/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Continued. Traffic here on site for pre-con with Alex and Northstar communications. No traffic elements in place.
02/28/2022 TRSP - ROW - Recurring Passed TDOT-EXCAV GENERAL INSPECTION - Closed. Site has been completed. Asphalt patching has been completed to satisfactory condition. No remaining issues.
01/27/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued Subcontractor vertical one on site working on antenna.
01/17/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. No activity on site by the contractor or subcontractors. Pole needs to be installed as well as cabinet.
12/28/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. No activity on site by the contractor or subcontractor
12/20/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. No activity on site by the contractor or subcontractors.
12/14/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. No activity on site by the contractors or subcontractors.
12/13/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. Subcontractor vertical one on site installing cage for Light pole foundation. And conduit.
12/08/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. Subcontractor Northstar on site along with Quail marking out patch locations.
12/01/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. Subcontractor Northstar on site tracing and installing electrical conduit.
05/14/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued-No activity
11/01/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Continued. No traffic elements in place.
11/30/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. No activity on site by the contractor or subcontractors.
02/28/2022 TRSP - ROW - Recurring Passed TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site.
11/24/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. No activity on site by either contractor or subcontractors.
01/27/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
11/23/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. No activity on site by either contractor or subcontractors.
01/17/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices removed from roadway, staged for set up/pickup.
11/20/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - North Star to begin bore from pole south of 26th to 26th north. Bore pit to be in bike lane of country club notified them if plated must be recessed can’t be on top on collector roadway. They will cold patch and backfill until slurry Monday. James deih will be onsite all day and make sure traffic control is removed by 1530 and work completed. Gas standby to be onsite today.
11/18/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. No activity on site by the contractor or subcontractor. No approved traffic control plan in place.
12/28/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices removed from roadway, staged for set up/pickup.
11/11/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. Feel Precon with Alex TEP North star and myself.
12/20/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Continued. No traffic elements in place or being used. VPs staged on the side of the road.
11/01/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. Work has not yet started. No activity by contractor or subcontractors.
12/14/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
10/29/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. James DEIH Ray and Nancy from vertical one Quail rep and TEP rep all on site for pre-con.
12/13/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
10/28/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued-No activity
12/08/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Continued. No traffic elements in place no activity on site. I’ll be back on this
10/01/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued-No activity
12/01/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site.
04/22/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued-No blue stake no activity.
10/29/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Continued. Quail barricade on site for pre-con.