Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T20RW02223

Parcel: Unknown


Addresses:

4090 E 3RD ST


Inspection Status: Passed

Inspection History: TRSP - ROW - Recurring

Permit Number - T20RW02223

Inspection Description - TRSP - ROW - Recurring

Inspection Status - Passed

Date Description Inspector Results Comments
12/18/2020 TRSP - ROW - Recurring Passed TDOT-EXCAV GENERAL INSPECTION - All construction completed. All work performed and dirt shoulder. Appears of work out of future sidewalk area. Street unaffected. Dirt shoulder restored to original condition. Special note:electric pedestal installed as per permit drawings.
12/18/2020 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Continued
11/10/2020 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - New pool footing excavated and formed up. New conduit for TEP run being installed.
11/10/2020 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Barricade set up along curb to protect workers and shoulder area.
11/10/2020 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Footing for Pole excavated. Workers forming up for concrete footing.
11/10/2020 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Barricade set up a long curb. I’ll work being performed in dirt shoulder.
11/05/2020 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Preconstruction meeting at site. Appears roadway will not be affected. No sidewalk in area. Reviewed location of Pole and equipment pads. Anticipated start date first to middle of next week.
11/05/2020 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Not Ready for Inspection