Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/02/2021 | TRSP - ROW - Recurring | Passed | TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site. | |
04/01/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Traffic control devices removed from roadway, staged for set up/pickup. Barricades are also set up around the new sidewalk that was just bored and waiting for form removal. | |
03/31/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Traffic control devices removed from roadway, staged for set up/pickup. Area of work cleaned up. True Net cleaned and beautified NW corner of Seneca and Ralph. Team Fishel will be back to remove sidewalk forms tomorrow. | |
03/31/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Traffic control is set according to plan. Minor changes made. Team Fishel to pour sidewalk that was out of spec. Also got True Net fixing broken conduit on NW corner of Seneca and Ralph. | |
04/02/2021 | TRSP - ROW - Recurring | Passed | TDOT-EXCAV GENERAL INSPECTION - All work complete, no concerns area has been cleaned out and forms of previously poured curb have been removed. Area has been beautified. | |
03/30/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Continued. No traffic control barricades blocking entrances to neighbor properties. | |
04/02/2021 | TRSP - ROW - Recurring | Passed | TDOT-EXCAV GENERAL INSPECTION - Cell tower system completed. Site cleaned up. Sidewalk panels replaced. Meter installed. Permit closed. | |
02/22/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Waiting on contractor to complete the power conduit run at the power pole. TEP requires a pedestal to be placed near the pole. | |
04/01/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - All components of this new tower side are installed. Section of sidewalk was removed and re-placed. Forms at sidewalk still need to be removed and grade around sidewalk needs to be completed, asphalt repaired at pothole. Dirt shoulder at power pole at power run has been restored. | |
02/01/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Barricade set up around pad mount a transformer tie in location. | |
02/22/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - All construction at the tower site is completed. Sidewalk not affected. Roadway not affected. The area where the pedestal is being placed near the power pole is barricaded off and waiting for TEP to complete their work. | |
01/13/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Not Ready for Inspection. Precon at site. Existing sidewalk. Needs change in power run location. Starts in couple of weeks. | |
02/01/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - New pole installed. All boxes set. Section of sidewalk replaced. Roadway needs repair at pothole. Workers are still working at power tying into existing pad mounted transformer. | |
04/02/2021 | TRSP - ROW - Recurring | Passed | TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site. | |
10/30/2020 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Not Ready for Inspection.No blue steak. Location of Paul Mark. No sign of work. | |
10/30/2020 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Not Ready for Inspection |