Inspection Status: Continued
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 09/15/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
WORK ON 22ND IS COMPLETE. MET ONSITE TO DISCUSS ASPHALT PATCHES. THEY WILL BE 4ft BY HOWEVER LONG THEY NEED TO BE. TOLD THEM TO REMOVE TRAFFIC CONTROL ON 22nd. |
| 09/10/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
contractor on site multiple locations traffic control at each location is ok |
| 06/19/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
CONTRACTOR ON SITE. REMINDED THEM TO TAKE PICS OF ANY DAMAGES BEFORE THEY START |
| 05/20/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
PRECON WITH NPL AND SWGAS FOR NEIGHBORHOOD GAS MAINLINE AND SERVICES. 22ND IS UNDER MORATORIUM MUST RECESS PLATES, SLURRY BACKFILL ON 22ND |
| 05/18/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Not ready for Inspection |
NO WORK VISABLE |
| 04/29/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Not ready for Inspection |
NO WORK |