Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 05/08/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
Sidewalkpanels replaced. Forms removed. Completed. Closed. |
| 04/22/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Boring completed. 2 panels of sidewalk removed with barricades. Forms set and grade compacted. OK to pour. |
| 04/01/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Blue stake completed. Sidewalk will be affected. Will need to pothole in Pime St. Will bore across Pima St. |
| 04/01/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Contractor requested a precon for 4/01/20 at 7 am. |