Permit: T20RW01680

Parcel: Unknown


Addresses:

3400 S PANTANO RD


Inspection Status: Re-inspection required

Inspection History: TRSP - ROW - Recurring

Permit Number - T20RW01680

Inspection Description - TRSP - ROW - Recurring

Inspection Status - Re-inspection required

Date Description Inspector Results Comments
05/18/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
10/12/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Not Ready for Inspection
05/09/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
10/01/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Not Ready for Inspection
05/04/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
09/07/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Not Ready for Inspection
05/02/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan. ADA temp sidewalk is ok
08/16/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Not Ready for Inspection
05/02/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices removed from roadway, staged for set up/pickup.
07/28/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Not Ready for Inspection
04/29/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
06/01/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Not Ready for Inspection
09/21/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Not Ready for Inspection no one onsite
09/13/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Contractor not onsite at this time.
07/20/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Velex onsite working on rf for site and cabinet. Chain link needs removal from sites mast atm and light still needed as well.
07/15/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Pre warners facing traffic on side streets. No more lane switches being used. Emailed quail and velex to remove all traffic control from median and side streets that are no longer needed. Only barricades needed onsite will be for south bound right lane closure on pantano.
07/14/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Not Ready for Inspection
07/05/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. Sidewalk panels have been replaced. Waiting on cabinet install
06/30/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Spoke to Michael smith with velex. Fence to be removed and sidewalk opened for access. Barricades to be removed from pantano and open roadway.
06/28/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued
04/28/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Not Ready for Inspection
12/17/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Not Ready for Inspection
06/21/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Framed sidewalk. Grade is ready to pour.
06/17/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Waiting to hang pole. Time was for 1115. Sidewalk panel restoration is in rejection. North panel 3.7% south panel 5.2%. Over a 1/4” kicker on north panel side to existing. Notified velex of rejection. Requested sand bags or waddles be placed in scupper north of site for weekend rain.
06/10/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Velex placing concrete. Short load redimix placing concrete. Concrete temp 96°f. Sam k deih and James Flores deih didn’t reject due to temperature will call electric shop to confirm acceptance. Aci spec is 95°f MAXIMUM per ACI 305.1 1-14 concrete acceptance. 18 bags of ice added to water by velex. Temp at 1229.
06/10/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued
09/21/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices removed from roadway, staged for set up/pickup.
05/18/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. Waiting on concrete
09/13/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control onsite, out of roadway at this time. No work going on at this time.
05/09/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued
08/22/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control needs maintenance
05/02/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. They are removing the street light pole base. They cannot get concrete for new base for approximately 8 weeks. They will be removing 2 concrete sidewalk panels that they broke while removing base. I asked them to put a temp patch over those panels that are removed so we could remove traffic control until they can get materials to complete job. I asked Dan to email Velex for the official records
07/20/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
04/29/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Velex removing pole. Ada to be set up with sb lane closure 24 hours.
07/18/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices removed from roadway, staged for set up/pickup.
04/20/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Not Ready for Inspection
07/15/2022 TRSP - ROW - Recurring Passed TDOT-Routine Barricade Inspect - Traffic control devices removed from roadway, staged for set up/pickup.
03/23/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Not Ready for Inspection. Underground has been completed
07/14/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is on roadway with no work being performed
04/09/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Not Ready for Inspection
12/10/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
02/24/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Not Ready for Inspection
07/14/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control needs maintenance. Barricade company was called to turn right lane closed signs in median southbound. Devices in curb lane.
02/22/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Not Ready for Inspection
07/05/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices removed from roadway, staged for set up/pickup.
01/31/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. Some patches have been done.
06/30/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control needs maintenance ada wall not proper. Barricades not bagged. Traffic control needs take down in median.
01/26/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Not Ready for Inspection
06/28/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
01/20/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Not Ready for Inspection. Pole needs installed and pavement repair is needed
06/21/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Continued
01/10/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Not Ready for Inspection
06/17/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
06/10/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan. Some barricade ran over notified velex to notify quail and have replaced
12/29/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. Waiting for permanent repair. Street light has not been installed.
06/10/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
12/17/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. Met with r directional and Tom to discuss pavement and slurry requirements
06/08/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control needs maintenance
12/10/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. I called contractor to maintain all potholes on pantano and on escalante
05/25/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
10/26/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Not Ready for Inspection
04/09/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. On site
04/09/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.