Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/14/2022 | TRSP - ROW - Recurring | Passed | TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site. | |
09/01/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Continued-Pole is up. | |
02/11/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Traffic control is set according to plan. | |
08/31/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Continued-No activity today. | |
02/11/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site. | |
08/26/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Continued-No activity | |
02/09/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Traffic control is set according to plan. | |
08/13/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Continued-Pre-con with Velex Peter Smith, James Flores DEHI, Jeff Williams All American Underground and Luis from TEP. Went over project details. | |
02/02/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Traffic control is set according to plan. | |
08/06/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Continued- No activity | |
01/28/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Traffic control is set according to plan. | |
07/29/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Continued-No activity permit expired 7/27/21 | |
01/27/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Traffic control is set according to plan. | |
06/08/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Continued-No activity | |
02/14/2022 | TRSP - ROW - Recurring | Passed | TDOT-EXCAV GENERAL INSPECTION - Sidewalk curb and asphalt restored. Landscaping restored. Pole placed and electrical passed by James Flores. Site passes final ROW inspection. | |
02/11/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Asphalt restored and sidewalk. Curb restored. Area restored from water line break during bore. Site passes final ROW pending barricade pickup and steeet cleanup. | |
02/11/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Velex restoring asphalt. Using low volume approved by Dan Robertson. | |
02/09/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Velex pouring curb with approved concrete. Forms to be pulled today. Asphalt set to be restored Friday. | |
02/02/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Velex removed 4” material under asphalt and placing AB compaction terror 100% by testing. Formed curb for pour set 2/9/2022. Sidewalk now open. Sam and James deih onsite with contractors. Velex will call when compaction completed and email reports from WTI | |
01/28/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Velex preparing to pour sidewalk. Sidewalk subgrade passed compaction. Pour scheduled for 1100. Cemex had a mix up and arrived at 1230. Velex has cure onsite. It is extremely windy. Panels to be 4’. Curb compaction failed this morning and will be retested at 1400. James deih was onsite while they worked on entenna and sidewalk. | |
01/25/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Traffic control is set according to plan. | |
05/24/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Continued-No activity | |
01/27/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Velex compacted under curb and sidewalk. WTI late and coming for compaction. Will email proctor and compaction results including failing test done yesterday. Concrete for sidewalk restoration set for tomorrow at 1100. | |
01/25/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Met with velex and Dan Robertson. Curb and sidewalk to be restored from water line break. Asphalt to be restored. Requiring one point proctor and compaction tests for under curb att 100% and 95% undersidewalk with use of native material. | |
12/07/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Continued. Traffic control set up on Irvington during holiday restrictions | |
11/23/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Continued. Call has been installed but work is still being performed south of pole sidewalk panels have been removed | |
11/12/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Continued-Pole is up. | |
11/03/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Continued-Pole is up. | |
10/05/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Continued-No activity going on. | |
09/30/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Continued-Foundation in. | |
09/24/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Continued-Foundation poured. | |
09/09/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Continued-No activity going on today. | |
05/11/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Continued-No activity | |
12/07/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Correction Required. Traffic control with set up on Irvington during holiday restrictions quail construction stated that the Velex did some work last night |