Inspection Status: Not ready for Inspection

Inspection History: TDOT-EXCAV GENERAL INSPECTION

Date Description Inspector Results Comments
04/02/2020 TDOT-EXCAV GENERAL INSPECTION Not ready for Inspection NO WORK
04/02/2020 TDOT-EXCAV GENERAL INSPECTION Approved COMPLETE
NO ISSUES AT THIS TIME
03/18/2020 TDOT-EXCAV GENERAL INSPECTION Continued COMPLETED BACKFILL
03/16/2020 TDOT-EXCAV GENERAL INSPECTION Continued WATCHED THEM BACKFILL PASSED COMPACTION TEST
MADE IT TO BOTTOM OF GAS LINE
03/11/2020 TDOT-EXCAV GENERAL INSPECTION Continued MET CONTRACTOR ONSITE
20 FOOT EXCAVATION AT MANHOLE. TA SAYS IF USING NATIVE A DENSITY TEST IS REQUIRED AT LEAST EVERY 5 FT. IF AB IS USED AND COMPACTED PROPERLY WE CAN TEST THE LAST 5 FT.
03/05/2020 TDOT-EXCAV GENERAL INSPECTION Continued INSTALLING SEWER ON SHOULDER
03/03/2020 TDOT-EXCAV GENERAL INSPECTION Not ready for Inspection NOT IN ROW