Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 05/18/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
Final Inspection. No Further issues. |
| 04/22/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Discussed DW Apron with GC. Will need to pour curb seperately from DW Apron. Will call for form/grade inspection. 4/24 or 4/27. |
| 04/21/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Dutch Brothers Coffee. Phone call with MW Morrisey. Will visit 8am 4/22 |
| 04/17/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Form Check. OK to pour 4/21 |
| 04/08/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Form check on ADA ramps. Will be pouring inside property 4/9. Pouring ramps early next week. Will return for next form check on SW. |
| 04/02/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Future Dutch Bros Coffee. Form check on remainder of curb. OK to pour. Will call for form check on ADA ramps when ready. Possibly Friday. |
| 02/17/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Electrician beginning to work on running conduit across alley to pole. Will plate overnight. |