Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 04/02/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
Work Complete. No Issues. |
| 02/19/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Visit to check placement of Business Access signs requested by Business owners along. East side of job. Signs are up. Devices will be pulled on Friday after Temp Striping completed. |
| 02/12/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Meeting with Hunter Construction to discuss milling limits of Country CLub. Will shift milling limits to south to match milling limits of future patch to be done by Tucson Water contractor. SWG on site sawcutting to expose extra few feet of main. SWG must replace 4' section of main in addition to the gas service that was hit by Hunter. Patch will be done Friday. Mill and overlay will be week of 2/17. Tucson Asphalt is paving subcontractor for Hunter Construction. |
| 02/10/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Hunter Contracting installing TW Main hit Gas service on 2/6. Will be submitting TC plan to address work needed to restore service to customer before continuing with main installation. Email sent to PIO and Gloria S. |
| 02/03/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Water Line install. High line installed, waiting on BACT. Will be back monday to begin 6" Main Install. Road is under moratorium and will require 2" mill and replace on 50' either direction of edge of trench location. TDOT 2 Mix. Hunter Contracting is working for Tucson Water. |