Permit: T20RW00260

Parcel: Unknown

Inspection Status: Re-inspection required

Inspection History: TRSP - ROW - Recurring

Permit Number - T20RW00260

Inspection Description - TRSP - ROW - Recurring

Inspection Status - Re-inspection required

Date Description Inspector Results Comments
01/17/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
Barricades from street removed only alley way being worked on.
12/20/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Northstar excavating where bore will come out. Scratched what appears to be an unmarked telephone line. Notified Dan Robertson and asked Northstar if they will notify blue stake of an unmarked utility.
01/17/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
12/20/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - TPD onsite. Crew to begin bore from alley to swf location for electric conduit. When boring from alley east to pedestal they will be over top of water main. Luis from tep asked them to encase conduit in concrete that is above 36” over top of water main. Crossing water main by swf will need to be under main. 8” main top of pipe is 36” at main 43” in alley. Alley run will be at 29-30” line at swf run from alley south on west side of road will be at 56” minimum under main.
01/14/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
12/17/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Northstar preparing potholes and digging for pedistole for bore Monday. Shrubs and landscaping near tep approved pole for riser meeting Daniel Robertson on site to discuss.
01/03/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
12/07/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - PreCon with Northstar nexius velex and deih. Dan Robertson onsite. Pole to be placed 7’ west of stop sign and signs added to new swf pole. City arborist to be notified of tree grown into ROW. Homeowners vehicle parked in ROW where work zone is located. Trafficade to draw new plan with flaggers and no parking signs. Homeowner will need to move vehicle from work zone. New notifications to be sent out will upload when completed.
06/11/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - All elements of Nepal have been moved into rear alley and off of property owners easement. Work starts on Monday but protesting has started today.
12/30/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
06/03/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Pre-con held on site. Notices will be going out today. No issues, but I imagine the neighborhood will not be real happy about this pole once they receive the notices
12/28/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Continued - Trafficade shadow truck/Flagger on site. Traffic Control devices staged for setup.
03/04/2022 TRSP - ROW - Recurring Passed TDOT-EXCAV GENERAL INSPECTION - New swf placed. Stop sign and street on pole. Light placed per plans. James deih passed electrical inspections. ROW passes final inspection. Landscaping and asphalt restored.
02/28/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Velex working on swf. Stop sign placed on new pole. Ada wall to be removed. Nick and city council called me and want light added to pole per plans. Material ordered for electrical to be ran and mast arm and light will be placed in the next couple of days.
06/01/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Pole location has been marked out. No pre-con has been set yet
12/20/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
02/28/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Velex placed swf pole. Pole secured. Ada wall to be removed from site today. Homeowner demanded rf reading. TPD onsite
02/25/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Caps placed around foundation and electrical box. Ray to hang pole Monday pending concrete breaks.
02/22/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Venezuelan onsite to pour caisson. 75°f 5.0” slump. 6 cylinders made. Mix was 3000 psi will do a 6 day break and a 14 if needed. Pole set to go up Monday. Vibration used during pour. Waiting for slurry.
02/22/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - TPD on site for day. James deih arrived at 0900 and did rebar and electrical inspection. Pour to be at 1300 followed by slurry 1330.
02/21/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Velex completed work for the day and cleaned up site. Pour concrete tomorrow at 1300 after electric shop inspection
03/04/2022 TRSP - ROW - Recurring Passed TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site.
02/21/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Velex placing ground rods and prepping for pour tomorrow. TPD onsite. Home owner harassing workers and officer. Velex has filed a report with TPD on site.
02/28/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
02/18/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Velex finished pole foundation hole and dropped in rebar and sonna tube. Trenched for electrical and fiber boxes. Prepping for pour on Tuesday.
02/28/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
02/18/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Velex vacuum trenching for pole foundation. Will trench for electrical and fiber boxes as well. Rebar to be placed today. Concrete set for Tuesday. TPD onsite in case residents entire workzone again.
02/25/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices removed from roadway, staged for set up/pickup.
02/17/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Arborist came and cut the tree to be visible for new stop sign on swf. Multiple homeowners came out. Grand daughter or daughter of homeowner at 3769 Calle Fernando calling everyone terrorists and refusing to leave workzone. Another man got in Rene from velex face and stood under tree while cutting being done and refused to leave workzone. Velex called TPD they said officer enroute. Recommended velex caution tape off entire workzone. Fencing placed around swf foundation hole that is 7’ deep since they refused to leave workzone. All residents have left after they found police were enroute. Tree has been trimmed by city approved arborist to make clear view of new stop sign on pole. Work to proceed. Tree is on private property but over grown into ROW .
02/22/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
02/17/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Velex to begin vacuum trenching for pole. Asked them to move truck to roadway and out in front of homeowners house. Fencing on site for around trench.
02/22/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
05/10/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Work has not begun on new pole
12/20/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
01/24/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Walk with velex to discuss protestors and pole placement along with restoration
02/21/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
01/21/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Northstar has completed electrical run for proposed swf. Landscaping has been restored and ped placed in alley. Gravel placed around stop sign. Awaiting pole installation. Asphalt restored with approved mix.
02/21/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
01/19/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Northstar installed pedestal. Gravel needed near stop sign for finishing restoration.
02/18/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
01/17/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Northstar cleaned up ROW landscaping and is remove piles. Gravel to be brought tomorrow. Home owner again came out demanding notifications and permit I notified her I will not be providing them she may contact the city attorney or refer to the city website. She again threatened me with lawyer and I stopped speaking. Notified the city of the issue. Northstar requesting officer on site for remainder of work days. All rocks and landscaping look nice pictures are date and times stamped.
02/18/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
01/17/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Northstar pouring meter ped pad in alley way. Home owner came out and complained of rocks and electrical conduit coming above ground . I stated I can have rocks removed or placed nicely along curb. She proceeded to follow me down alley screaming at me and I asked her to please leave the active construction zone due to heavy machines and plates being loaded for removal. She refused until Northstar stated they were going to contact TPD and she left to house. Pipe was cut 4” below grade and backfilled. Rocks were neatly stacked along curb still in ROW. CMU wall in homeowners yard is 6’ into right of way and edge of curb is ROW cut off. All ROW markings were removed by neighborhood and paint was removed as well. Northstar will rake the area and bring gravel tomorrow to fully restore landscaping until pole is placed.
02/17/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
01/17/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - 3769 Calle Fernando home owners daughter outside calling everyone baby killers and terrorists. Told us she is taking legal action against city and all individuals onsite. I told her if she has any questions to notify the city transportation department or utility coordinator and directed Northstar to have no contact with her any longer. Work being done in alley way pour meter ped today installing tomorrow. Plates and barricades and clean up to be done today until pole installation comes. Notified Dan Robertson of the issue nick g is off for the holiday.
02/17/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
01/14/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Plates placed in alley over trench awaiting TEP inspection. Forming meter pedestal pad. Asphalt patch that was placed crAcked on edge.
01/24/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site.
01/03/2022 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Luis from TEP wanted pedestal moved 3’ south. Called nick g city utility coordinator and he was unaware of any approved redlines placing pedestal on east side of roadway. Plans will be redlined to place meter pedestal 16’ west of TEP pole in alley way.
01/21/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site.
01/19/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices removed from roadway, staged for set up/pickup.
12/30/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Northstar forming meter pedestal. Possible installation of riser. Requested trench in alley be backfilled for the weekend due to rain chances.
01/17/2022 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
12/28/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued - Contractor not yet on site. Conduit in, bore pit and receiving pit plated. Tree near electrical cabinet on east side of Calle Norte has been trimmed.
03/30/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - No work on pole has started.
12/17/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.