Inspection Status: Partial Approval
Inspection History: FIRE SPKLR - OH PIPING & HYDRO
| Date |
Description |
Inspector |
Results |
Comments |
| 03/15/2021 |
FIRE SPKLR - OH PIPING & HYDRO |
|
Partial Approval |
1. 3rd floor 200 lb pressure test approved via face time. Placement will have to be verified at the final. |
| 03/15/2021 |
FIRE SPKLR - OH PIPING & HYDRO |
|
Approved |
We will need to do a complete field verification at final since most hydro were witnessed from IPHONE and placement could not be verified. |
| 12/31/2020 |
FIRE SPKLR - OH PIPING & HYDRO |
|
Partial Approval |
1. 2nd floor 200 lb pressure test approved via face time. Placement will have to be verified at the final. |
| 12/15/2020 |
FIRE SPKLR - OH PIPING & HYDRO |
|
Partial Approval |
1. First floor is approved. 220lb ohpt at 11:30 am. |