Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: FIRE SPKLR - UG, PIPING, HYDRO
Permit Number - T20FC00297
Inspection Description - FIRE SPKLR - UG, PIPING, HYDRO
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/26/2021 | FIRE SPKLR - UG, PIPING, HYDRO | Approved | ||
01/07/2021 | FIRE SPKLR - UG, PIPING, HYDRO | Partial Approval | Intermediate building riser and 10' of pipe 215 PSI | |
08/19/2020 | FIRE SPKLR - UG, PIPING, HYDRO | Not ready for Inspection | last 50' of pipe to hydrant on NE corner of existing building not in yet. | |
07/08/2020 | FIRE SPKLR - UG, PIPING, HYDRO | Partial Approval | Observed 60' from main east to first 90* turn. | |
06/30/2020 | FIRE SPKLR - UG, PIPING, HYDRO | Partial Approval | 208 PSI for 2 hours. Still need to see 4" and 6" lines that head east to building under pressure. |
|
06/29/2020 | FIRE SPKLR - UG, PIPING, HYDRO | Cancelled | Spoke with Noberto from Kazal, he said he did not have an inspection for today. | |
06/26/2020 | FIRE SPKLR - UG, PIPING, HYDRO | Partial Approval | -Observed tie in to 4" on NW side of existing OH building -Observed 100' of 6" to hydrant on north side of existing OH building -Observed 55' of 6" from 6"tee to hydrant on west side of property next to the road |
|
06/23/2020 | FIRE SPKLR - UG, PIPING, HYDRO | Partial Approval | From 80' south of 6" tee to northwest corner of existing OH building, 6" is reduced to 4" 60' from building. |
|
06/17/2020 | FIRE SPKLR - UG, PIPING, HYDRO | Partial Approval | Inspected from second 45 degree turn to 80' past 6" T that went east toward building. Inpection done via Facetime. | |
06/17/2020 | FIRE SPKLR - UG, PIPING, HYDRO | Partial Approval | 240' of fire line on North side of project was inspected and then buried. TFD did not see this portion under pressure, GRANITE TO ACCEPT FULL RESPONSIBILTY AND LIABILITY FOR UNDERGROUND FIRE LINES AS TFD WILL NOT WITNESS ALL HYDRO TESTS. 6/10/2020 We saw 70ft to the hydrant as well as the T that goes south 6/12/2020 through both 45 degree turns heading south 6/17/2020 |
|
06/16/2020 | FIRE SPKLR - UG, PIPING, HYDRO | Not ready for Inspection | The trench was dug, however there was no pipe installed to inspect |