Case: T20DV06145

Parcel: 11504490A


Addresses:

1031 N PARK AV

Inspection Status: Approved

Inspection History: INSP - INITIAL CODE ENFORCMENT

Date Description Inspector Results Comments
09/14/2020 INSP - INITIAL CODE ENFORCMENT Approved PRIOR TO VISITING SITE IT WAS DETERMINED THAT THE COMPLAINTS WERE FOR THE NEW COMPLEX BEING CONSTRUCTED AT S/W CORNER OF PARK AND SPEEDWAY. I HAD INSPECTED THE PROPERTY ON 9/03/2020, CONTACTED CLAYTON TREVYLLIAN WHO IN TURN PUT ME IN CONTACT WITH LISA BOWERS WHO INFORMED ME THAT THE CONTRACTORS HAVE RECORDED EARLY MORNING STARTSUNDER PERMIT #T20RW04682. THE NEXT EARLY MORNING POUR WAS DATED FOR 9/09/2020. THERE ARE NO VIOLTIONS. COMPLIANCE / CLOSE CASE.