Inspection Status: Approved
Inspection History: BUILDING - PROGRESS
| Date |
Description |
Inspector |
Results |
Comments |
| 01/12/2022 |
BUILDING - PROGRESS |
|
Approved |
Approved |
| 11/03/2021 |
BUILDING - PROGRESS |
|
Partial Approval |
Partial approval for new gas line and pressure test ok for clearance SWG |
| 08/04/2021 |
BUILDING - PROGRESS |
|
Not ready for Inspection |
NR, (caisson foundations for sign boards and light poles) |
| 08/03/2021 |
BUILDING - PROGRESS |
|
Partial Approval |
- Partial, electrical conduit for 9 light poles and trash enclosure, okay to backfill |
| 07/08/2021 |
BUILDING - PROGRESS |
|
Partial Approval |
Partial, no inspection today. |
| 06/22/2021 |
BUILDING - PROGRESS |
|
Partial Approval |
PARTIAL INSPECTION FOR REBAR |