Inspection Status: Passed
Inspection History: COT - LCBU - Framing
Permit Number - T20CM08455
Inspection Description - COT - LCBU - Framing
Inspection Status - Passed
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/18/2022 | COT - LCBU - Framing | JBURGE | Approved | Entered by RSALDAT1 - |
| 11/12/2021 | COT - LCBU - Framing | JBURGE | Partial Approval | Entered by NGARCIA3 - Partial. From manhole number five to manhole number six. |
| 11/08/2021 | COT - LCBU - Framing | JBURGE | Not ready for Inspection | Entered by VVERA1 - Not ready, will reschedule for 10 November |
| 10/07/2021 | COT - LCBU - Framing | JBURGE | Not ready for Inspection | Entered by RSALDAT1 - Not ready. South exterior portion of building is not ready. |
| 09/30/2021 | COT - LCBU - Framing | JBURGE | Not ready for Inspection | Entered by VVERA1 - Not ready. Contractor cancelled, will reschedule for 1 October. |
| 09/27/2021 | COT - LCBU - Framing | JBURGE | Not ready for Inspection | Entered by NGARCIA3 - Not ready. Level #2 interior framing. Contractor cancelled. |
| 09/22/2021 | COT - LCBU - Framing | JBURGE | Not ready for Inspection | Entered by RSALDAT1 - Not ready. Framing on Level #2 incomplete. Contractor cancelled. |
| 09/15/2021 | COT - LCBU - Framing | JBURGE | Not ready for Inspection | Entered by NGARCIA3 - . Not ready. Interior framing on Level #1: will recall for inspection 16 September. |
| 09/13/2021 | COT - LCBU - Framing | JBURGE | Not ready for Inspection | Entered by NGARCIA3 - . Not ready. Contractor cancelled, will reschedule for 15 September. |
| 09/03/2021 | COT - LCBU - Framing | JBURGE | Not ready for Inspection | Entered by VVERA1 - 01035. Not ready. Contractor cancelled. |
| 08/24/2021 | COT - LCBU - Framing | JBURGE | Partial Approval | Entered by VVERA1 - 01035. Partial. West wall exterior framing at Level #2. Ok to hang exterior sheathing on progress areas. |
| 07/20/2021 | COT - LCBU - Framing | JBURGE | Not ready for Inspection | Entered by RSALDAT1 - Not ready. Will reschedule for 23 July. |