Inspection Status: Passed
Inspection History: COT - LCME - Mechanical Above Ceiling
| Date |
Description |
Inspector |
Results |
Comments |
| 12/10/2021 |
COT - LCME - Mechanical Above Ceiling |
DMUNIZ |
Approved |
Entered by VVERA1 - Approved |
| 11/15/2021 |
COT - LCME - Mechanical Above Ceiling |
JBURGE |
Partial Approval |
Entered by RSALDAT1 - Partial, Smoke test on Hood to Grease duct connection complete ok to fire wrap.
|
| 11/05/2021 |
COT - LCME - Mechanical Above Ceiling |
DMUNIZ |
Correction Required |
Entered by RSALDAT1 - ) corrections required, smoke test on Hood to duct connection failed. Multiple locations where welds are incorrect, repair, re-test and call in inspection when corrections are complete.
|
| 11/04/2021 |
COT - LCME - Mechanical Above Ceiling |
DMUNIZ |
Partial Approval |
Entered by NGARCIA3 - Partial, no inspection required today, contractor rescheduled.see previous notes. |
| 08/18/2021 |
COT - LCME - Mechanical Above Ceiling |
DMUNIZ |
Partial Approval |
Entered by VVERA1 - PARTIAL, Above ceiling in Office Building 2nd floor inspected. Note: install seismic tie for all mechanical fixtures in acoustic ceiling locations. Check interconnections for all rigid to flex duct connections. Properly band where needed. |