Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: MECHANICAL - FINAL
Permit Number - T20CM07264
Inspection Description - MECHANICAL - FINAL
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/28/2022 | MECHANICAL - FINAL | Approved | 1090.AP | |
01/21/2022 | MECHANICAL - FINAL | Partial Approval | pa H20 heaters ok in units 41, 42 in bldg 11, and 43, 44, 45 in bldg 12. |
|
12/15/2021 | MECHANICAL - FINAL | Approved | Ap 47 Hvac units for apts and 2 for laundries all complete 47 water heaters on back order till 2022. |
|
12/08/2021 | MECHANICAL - FINAL | Partial Approval | pa Hvac for unit L8 - bldg 8 - laundry room - ok |
|
12/07/2021 | MECHANICAL - FINAL | Partial Approval | Pa Hvac in unit #20 in bldg 1 - ok. Hvac in laundry room L5 in bldg 5 - ok |
|
12/03/2021 | MECHANICAL - FINAL | Partial Approval | pa Hvac for unit # 18 in bldg 1 - ok |
|
12/02/2021 | MECHANICAL - FINAL | Partial Approval | Hvac for unit# 19 in bldg 1 - ok | |
11/30/2021 | MECHANICAL - FINAL | Partial Approval | pa Hvac for unit# 16 in bldg 2 - ok |
|
11/29/2021 | MECHANICAL - FINAL | Partial Approval | pa Hvac for unit # 15 in bldg 2 - ok |
|
11/23/2021 | MECHANICAL - FINAL | Partial Approval | pa Hvac in units 12 and 13 - in bldg 3 - ok |
|
11/19/2021 | MECHANICAL - FINAL | Partial Approval | pa Hvac for unit #11 in bldg 3 ok. |
|
11/18/2021 | MECHANICAL - FINAL | Partial Approval | pa Hvac in unit 47 in bldg 13 ok |
|
11/17/2021 | MECHANICAL - FINAL | Partial Approval | pa Hvac for unit # 46 In bldg 12 ok |
|
11/16/2021 | MECHANICAL - FINAL | Partial Approval | pa Hvac in unit #44 in bldg 12 ok. |
|
11/15/2021 | MECHANICAL - FINAL | Partial Approval | pa Hvac in unit # 45 in bldg 12 - ok |
|
11/12/2021 | MECHANICAL - FINAL | Partial Approval | Pa Hvac for unit # 43 in bldg 12 - ok |
|
11/10/2021 | MECHANICAL - FINAL | Partial Approval | pa Hvac in unit #39 in bldg 11 - ok |
|
11/09/2021 | MECHANICAL - FINAL | Partial Approval | pa Hvac for unit # 40 in bldg 11 ok |
|
11/09/2021 | MECHANICAL - FINAL | Partial Approval | pa Hvac in unit # 42 in bldg 11 |
|
11/05/2021 | MECHANICAL - FINAL | Partial Approval | pa Hvac for unit # 38 in bldg #10 - ok |
|
11/04/2021 | MECHANICAL - FINAL | Partial Approval | pa Hvac for unit# 37 in bldg 10 - ok |
|
11/03/2021 | MECHANICAL - FINAL | Partial Approval | pa Hvac for unit # 36 in bldg 9 ok |
|
11/02/2021 | MECHANICAL - FINAL | Partial Approval | pa Hvac for unit # 35 in bldg # 9 ok |
|
11/01/2021 | MECHANICAL - FINAL | Partial Approval | pa Hvac for unit #34 in bldg 10, ok. |
|
10/28/2021 | MECHANICAL - FINAL | Partial Approval | pa Hvac for unit # 10 in bldg 5 - ok |
|
10/27/2021 | MECHANICAL - FINAL | Partial Approval | pa Gas test in bldg 5 - units 8, 9, 10 - ok Hvac in units 8 and 9 - bldg 5 - ok |
|
10/25/2021 | MECHANICAL - FINAL | Partial Approval | pa Hvac for unit # 7 in bldg 5, ok. |
|
10/22/2021 | MECHANICAL - FINAL | Partial Approval | Pa Hvac for unit # 6 in bldg 4 ok |
|
10/20/2021 | MECHANICAL - FINAL | Partial Approval | pa Hvac in unit # 4 - bldg 4 ok |
|
10/18/2021 | MECHANICAL - FINAL | Partial Approval | pa Hvac in unit #3 in bldg 4 ok |
|
10/15/2021 | MECHANICAL - FINAL | Partial Approval | pa Hvac ok for unit # 2 in Bldg 4 |
|
10/13/2021 | MECHANICAL - FINAL | Partial Approval | Pa Hvac for unit # 1 in bldg 4 ok |
|
10/12/2021 | MECHANICAL - FINAL | Partial Approval | Pa Hvac for unit # 26 in bldg 6C ok |
|
10/11/2021 | MECHANICAL - FINAL | Partial Approval | pa Hvac ok for unit # 25 in bldg 6C |
|
10/08/2021 | MECHANICAL - FINAL | Partial Approval | pa Hvac for unit# 24 in bldg 6A ok |
|
10/07/2021 | MECHANICAL - FINAL | Partial Approval | pa Elec and Hvac for unit #23 in bldg 6A ok |
|
10/06/2021 | MECHANICAL - FINAL | Partial Approval | pa Hvac unit for unit# 22 in bldg 6B ok |
|
10/05/2021 | MECHANICAL - FINAL | Partial Approval | pa Hvac unit# 221 in building 6B ok |
|
10/04/2021 | MECHANICAL - FINAL | Partial Approval | pa Hvac ok on unit 29 - bldg 7 |
|
10/01/2021 | MECHANICAL - FINAL | Partial Approval | pa Hvac for unit# 27 in Bldg 7 ok |
|
09/30/2021 | MECHANICAL - FINAL | Partial Approval | pa Unit # 30 Hvac install complete. |
|
09/29/2021 | MECHANICAL - FINAL | Partial Approval | pa Unit # 28 elec and gas pack ok |
|
09/28/2021 | MECHANICAL - FINAL | Partial Approval | pa Hvac complete |
|
11/10/2020 | MECHANICAL - FINAL | Prior to Final Inspectn | AIR BALANCE REPORT REQUIRED (VENTILATION) |