Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
Permit Number - T20CM06822
Inspection Description - EXCAVATION/LAYOUT REBAR & ZON
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/01/2022 | EXCAVATION/LAYOUT REBAR & ZON | Approved | 2010, 1015, 1075, 1005, 1010, 1020. 2035, 1035. 2090, 1090 . Approved. See permit number T21CM00360. |
|
09/21/2021 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 1005, 1010. Partial. Retain wall on East and Northeast corner of building. | |
04/30/2021 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | PARTIAL - POURING 1ST FLOOR COLUMNS | |
03/26/2021 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Elevator lift, 20 to 28 feet, top out, with clean outs. | |
03/25/2021 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Concrete 2nd floor header for elevators. | |
03/19/2021 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | ||
03/17/2021 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Footings at south canopy. | |
03/16/2021 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | CANCELLED BY CONTRACTOR | |
03/05/2021 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | CANCELLED BY CONTRACTOR | |
02/25/2021 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Footings and foundations, gridlines A4 to H4. Footings at D.1-5 and D.8-5. | |
02/23/2021 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | PARTIAL FOOTINGS AT GRIDLINES B3 THRU G3 | |
02/22/2021 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | PARTIAL INTERIOR FOOTINGS, GRIDELINES B2 THRU G2 | |
02/19/2021 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | PARTIAL FOOTINGS AND FOUNDATION ON GRIDLINES H-1 THROUGH 4, ELEVATOR PIT WALLS | |
02/18/2021 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Footings and foundations on Gridline H – 1 through 4. | |
02/17/2021 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | PARTIAL ELEVATOR PIT, FOOTINGS AND FOUNDATION ON GRIDLINES A1 TO A4 | |
02/16/2021 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | CANCELLED BY CONTRACTOR |