Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
Permit Number - T20CM06675
Inspection Description - EXCAVATION/LAYOUT REBAR & ZON
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/18/2021 | EXCAVATION/LAYOUT REBAR & ZON | Approved | Partial, GL-Q exterior footing, 10 spread footings for building columns, 11 caisson footings for shade structure all ok for concrete placement. | |
03/17/2021 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | IVRS - RI canceled | |
03/16/2021 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | IVRS - AP canceled | |
03/15/2021 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | IVRS - AP canceled | |
03/10/2021 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial, Exterior footings, & Interior beam ties under slab for (GL 1-10, A-M) Except at depressed slab locations. Ok for concrete placement. | |
03/03/2021 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial approval for stage area only, ok to pour. Baptismal pool was by third party | |
02/17/2021 | EXCAVATION/LAYOUT REBAR & ZON | Approved | APPROVED FOR COLUNM LINE M AND BAPTISTRY ONLY | |
02/11/2021 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | NOT READY, FACE TIMED AT 9:02AM NO ANSWER | |
02/11/2021 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | PARTIAL, SIX FOOTING ON GL 11 AND FOUR ON GL 1 | |
02/10/2021 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | PARTIAL, REBAR AT BACK OF STAGE AREA (CONTINUATION OF STEM WALL) | |
02/04/2021 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | PARTIAL OK TO POUR EAST SIDE FOOTER ONLY |