Inspection Status: Approved
Inspection History: MECHANICAL - ABOVE CEILING
| Date |
Description |
Inspector |
Results |
Comments |
| 07/12/2021 |
MECHANICAL - ABOVE CEILING |
|
Approved |
APPROVED, above ceilings for following offices complete (207,227,231,232,2300 |
| 07/09/2021 |
MECHANICAL - ABOVE CEILING |
|
Cancelled |
IVRS - AP canceled |
| 07/02/2021 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
Partial, 2nd floor Inspections for following Offices complete. (208-233) all ok to drop ceiling tiles. |
| 07/01/2021 |
MECHANICAL - ABOVE CEILING |
|
Cancelled |
IVRS - AP canceled |
| 06/24/2021 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
Partial, 1st floor East lobby inspected and ok to install ceiling tiles. |
| 06/23/2021 |
MECHANICAL - ABOVE CEILING |
|
Cancelled |
IVRS - AP canceled |
| 06/15/2021 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
Partial, second floor inspections required. |
| 05/11/2021 |
MECHANICAL - ABOVE CEILING |
|
Approved |
Approved 2nd floor |
| 03/31/2021 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
Partial, 1st floor Hard duct above ceilings installed and sealed. |