Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date |
Description |
Inspector |
Results |
Comments |
| 03/31/2021 |
PLUMBING - ROUGH, SOIL |
|
Approved |
|
| 02/25/2021 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
Partial Approval for 3” water supply from meter to building |
| 11/17/2020 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
|
| 11/17/2020 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
Partial, Plumbing under slab tested and ok to backfill progress. |
| 11/12/2020 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
Partial, Main Trunk under slab tested and ok to backfill, branch lines to be inspected at a later time. |