Inspection Status: Approved
Inspection History: FRAMING
| Date |
Description |
Inspector |
Results |
Comments |
| 05/11/2021 |
FRAMING |
|
Approved |
Approved 2nd floor |
| 05/07/2021 |
FRAMING |
|
Partial Approval |
Partial, 2nd floor South exterior walls and offices inspected and ok to insulate and Sheetrock. |
| 04/27/2021 |
FRAMING |
|
Partial Approval |
Partial, rough frame installed and ok to Sheetrock 2nd floor North of stairwells. |
| 04/02/2021 |
FRAMING |
|
Partial Approval |
Partial, 1st floor framing complete ok to Sheetrock. |
| 03/31/2021 |
FRAMING |
|
Partial Approval |
Partial, 1st floor framing complete. |
| 03/30/2021 |
FRAMING |
|
Partial Approval |
Partial, Framing for Plumbing walls in Restroom locations and Janitors closet (Rooms -105,106,107,108,119,120) |
| 03/16/2021 |
FRAMING |
|
Partial Approval |