Inspection History Details
Permit: T20CM03193
Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/16/2020 | ENGINEERING - FINAL | Approved | Approved. | |
| 09/15/2020 | ENGINEERING - FINAL | Not ready for Inspection | Not ready. General contractor, dean. Has rescheduled inspection for tomorrow. Contact number for Alfonso is 373-3408. | |
| 09/15/2020 | ENGINEERING - FINAL | Not ready for Inspection | Not ready. Contractor owed fees was unable to reschedule for inspection will do so tomorrow | |
| 09/11/2020 | ENGINEERING - FINAL | Not ready for Inspection | Not ready. Dean at714-655-6486 please schedule all inspections as required. 09027, 09025 and 01090 have not yet been approved. Also T190T01184 has not been inspected. |