Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date |
Description |
Inspector |
Results |
Comments |
| 08/03/2022 |
PLUMBING - ROUGH, SOIL |
|
Approved |
Approved |
| 01/14/2022 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
partial, 1 1/4” waste line under administration building ok to backfill. |
| 04/01/2021 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
Partial, continued under slab plumbing for Hangar location. (Restrooms, wash stations, Janitors closet, Elevator Sump). Ok to backfill progress. |
| 03/18/2021 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
Partial, Connection to existing sewer line under existing building ok to progress. |