Inspection Status: Approved
Inspection History: ELECTRIC - UNDERGROUND
| Date |
Description |
Inspector |
Results |
Comments |
| 08/03/2022 |
ELECTRIC - UNDERGROUND |
|
Approved |
Approved |
| 01/14/2022 |
ELECTRIC - UNDERGROUND |
|
Partial Approval |
Partial, conduit raceways for under slab branch circuits in Administration Building ok to backfill. |
| 10/19/2021 |
ELECTRIC - UNDERGROUND |
|
Partial Approval |
Partial for underground from 2nd light pole on the north end approx 400’ long due south (west parking lot) |
| 07/01/2021 |
ELECTRIC - UNDERGROUND |
|
Partial Approval |
Partial for site lighting, from existing electric room approx 300’ in north parking lot. Also from existing electric room to transformers T3,T7,T8,T4, okay to backfill |
| 06/30/2021 |
ELECTRIC - UNDERGROUND |
|
Not ready for Inspection |
NR, cancelled by Contractor |
| 04/26/2021 |
ELECTRIC - UNDERGROUND |
|
Partial Approval |
Partial approval from gridline E-9 80’ north toward transformers 3,4,7, and 8 with conduit for site lighting then break for approximately 150’ commence trench again at 10’ south of gridline A along North side of building easterly to individual transformer locations including metal risers to each transformer. |
| 04/13/2021 |
ELECTRIC - UNDERGROUND |
|
Partial Approval |
PARTIAL for 180’ of exterior conduit from Gridline E9 to Gridline E2 on the Southside of building |