Inspection Status: Approved
Inspection History: FRAMING
| Date |
Description |
Inspector |
Results |
Comments |
| 05/09/2022 |
FRAMING |
|
Approved |
Approved, okay to insulate and cover |
| 03/24/2022 |
FRAMING |
|
Partial Approval |
Partial, tool shack 108, 111 ok to dry wall |
| 03/02/2022 |
FRAMING |
|
Partial Approval |
Partial at stairwell #2 east side, and furred wall at gridline B/7.1, okay cover |
| 02/25/2022 |
FRAMING |
|
Partial Approval |
Partial, Stairwell 1 and Hanger wall @ 7.1-B-C ok to proceed. |
| 02/17/2022 |
FRAMING |
|
Partial Approval |
PARTIAL, Stairwell #2 frame rough frame complete. |
| 02/16/2022 |
FRAMING |
|
Cancelled |
Cancelled by Contractor (rain) |
| 02/15/2022 |
FRAMING |
|
Partial Approval |
Partial, 2nd floor between Gridlines D and E - Gridlines 7.E3 to 9 |
| 02/04/2022 |
FRAMING |
|
Partial Approval |
Partial, 2nd floor between Gridline D and Gridline E, Gridline 7.E3 to Gridline 1 |
| 01/31/2022 |
FRAMING |
|
Partial Approval |
PARTIAL, floor level WALL FRAME FOR FOLLOWING ROOMS OK TO ONE SIDE SHEETROCK (LAB 106, 107, TOOL/STORAGE 108, 110, 111). |
| 01/19/2022 |
FRAMING |
|
Partial Approval |
Partial for break-room 121, janitorial room 120, mens and woman’s restroom’s. Okay to drywall progress areas |
| 01/18/2022 |
FRAMING |
|
Not ready for Inspection |
NR, cancelled by Contractor |
| 01/07/2022 |
FRAMING |
|
Partial Approval |
Partial for rooms 102, 103, 104, 105, pending north wall of room 105 plumbing. Okay to insulate and drywall progress areas |
| 12/23/2021 |
FRAMING |
|
Partial Approval |
Partial for Gridline B - 1 through 7.E3 and Gridline D - 1 through 7.E3 |