Permit: T20CM02980

Parcel: 13608032A


Addresses:

2200 S HOUGHTON RD


Inspection Status: Canceled

Inspection History: COT - LCBU - Excavation/Rebar/Zoning 

Permit Number - T20CM02980

Inspection Description - COT - LCBU - Excavation/Rebar/Zoning 

Inspection Status - Canceled

Date Description Inspector Results Comments
12/10/2021 COT - LCBU - Excavation/Rebar/Zoning  Canceled {Activity date: 12/10/2021; Status: Not Applicable; Inspector: ESTEVENS; Comment: Entered by VVERA1 - 1090. N/A. See permit number T19CM05078.

Close permit} ; {Activity date: 05/10/2021; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by RSALDAT1 - 1020 Grout. East side column. 5th lift. 16 to 20 feet. Top-out

} ; {Activity date: 03/01/2021; Status: Partial Approval; Inspector: TTREMBULAK; Comment: Entered by VLEON1 - Partial. Slab on grade area D, between grid lines 10-15, & G-K.} ; {Activity date: 02/22/2021; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by VLEON1 - Partial. Slab on grade for the following rooms, CT scan GEN rad, RF room, MRI, Cath lab, fire pump room.

} ; {Activity date: 02/19/2021; Status: Cancelled; Inspector: ESTEVENS; Comment: Entered by VLEON1 - CANCELLED BY CONTRACTOR} ; {Activity date: 02/12/2021; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by VLEON1 - PARTIAL, SLAB ON GRADE AREA B IS COMPLETE} ; {Activity date: 01/28/2021; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by VLEON1 - PARTIAL SLAB ON GRADE, NORTH WEST HALF OF SLAB IN AREA C} ; {Activity date: 01/12/2021; Status: Cancelled; Inspector: ESTEVENS; Comment: Entered by VLEON1 - CANCELLED} ; {Activity date: 01/08/2021; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by RSALDAT1 - Partial. Area A, north west section. Slab on grade.} ; {Activity date: 01/06/2021; Status: Cancelled; Inspector: ESTEVENS; Comment: Entered by VLEON1 - } ; {Activity date: 12/29/2020; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by VLEON1 - Partial. The west column of the ambulance canopy.

} ; {Activity date: 12/22/2020; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by RSALDAT1 - Partial. CEP area. 7th lift, 24 feet to top-out.} ; {Activity date: 12/15/2020; Status: Not ready for Inspection; Inspector: ESTEVENS; Comment: Entered by VLEON1 - NOT READY} ; {Activity date: 12/02/2020; Status: Not ready for Inspection; Inspector: ESTEVENS; Comment: Entered by PAHUMAD1 - Not ready.} ; {Activity date: 11/25/2020; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by RSALDAT1 - Partial. CEP area. 4th lift.} ; {Activity date: 11/19/2020; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by PAHUMAD1 - Partial. CEP area. Gridlines B-9 thru 14.5. Gridlines AA-11 thru 14.9, Gridlines 13.3-AA to B, gridlines 14.5-AA to B.} ; {Activity date: 11/16/2020; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by RSALDAT1 - Partial. CEP area, 2nd lift to 8 feet.} ; {Activity date: 11/05/2020; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by PAHUMAD1 - Partial. CEP area, fire riser room 1st lift.} ; {Activity date: 10/29/2020; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by RSALDAT1 - Partial. Stairwell #1, Lift 11, 40-44 feet. Stairwell #2, Lift 10, 36-40 feet.} ; {Activity date: 10/28/2020; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by RSALDAT1 - Stairwell #1, Lift 10, 36-40 feet. Stairwell #2, lift 9, 32-36 feet.} ; {Activity date: 10/27/2020; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by RSALDAT1 - Partial. Stairwell #1, lift 9, 32-36 feet. Stairwell #2, lift 8, 2832 feet.} ; {Activity date: 10/26/2020; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by RSALDAT1 - Partial. Stairwell 1, lift 8, 28-32 feet. Stairwell 2, lift 7, 24-28 feet.} ; {Activity date: 10/23/2020; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by RSALDAT1 - Partial. Stairwell #1, Lift 7, 24 to 28 feet. Stairwell #2, Lift 6, 20 to 24 feet.} ; {Activity date: 10/21/2020; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by RSALDAT1 - Partial. Stairwell 1, Lift number 4, 13 to 16 feet. Stairwell 2, Lift number 5, 16 to 20 feet.} ; {Activity date: 10/19/2020; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by RSALDAT1 - pa

Stairwells # 1 2 ok to grout 4th lift} ; {Activity date: 10/15/2020; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by RSALDAT1 - Partial. Stairwell 1&2, 3rd lift, 8 to 12 feet.} ; {Activity date: 10/14/2020; Status: Cancelled; Inspector: ESTEVENS; Comment: Entered by JSCHNEI2 - Cancel} ; {Activity date: 10/13/2020; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by JSCHNEI2 - Partial. Stairwell number one and number two, 2nd lift, 4 to 8 feet.

Block wall, gridlines AA-11 to AA-14.5} ; {Activity date: 10/12/2020; Status: Partial Approval; Inspector: JBURGE; Comment: Entered by VFLORES1 - Stem wall at 0"-24" for electric room and riser room. Ok to grout progress areas.} ; {Activity date: 10/09/2020; Status: Not ready for Inspection; Inspector: ESTEVENS; Comment: Entered by JSCHNEI2 - Not ready.} ; {Activity date: 10/08/2020; Status: Not ready for Inspection; Inspector: ESTEVENS; Comment: Entered by VFLORES1 - } ; {Activity date: 10/07/2020; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by JSCHNEI2 - Partial. Block wall, gridlines B-13.3 to F-13.3. Gridlines B-13.3 to B-12. Gridlines A-8 to A-9, A-9 to B-9, 1st lift, 4feet.} ; {Activity date: 10/02/2020; Status: Partial Approval; Inspector: TTREMBULAK; Comment: Entered by JSCHNEI2 - Partial approval. Stairwell number three (west side) final lift @ 44’-48’.} ; {Activity date: 10/01/2020; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by RSALDAT1 - Partial. Stairwell number three, 11th lift 36 to 40 feet. Stairwell number four, 11th lift, top out} ; {Activity date: 09/30/2020; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by RSALDAT1 - Partial. Stairwell number four, lift number 11, 36 to 40 feet. Stairwell number three, lift number 10, 32 to 36 feet.} ; {Activity date: 09/29/2020; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by RSALDAT1 - Partial. Stairwell number three, ninth lift, 32 to 36 feet. Stairwell number four, 10th lift, 36 to 40 feet.} ; {Activity date: 09/28/2020; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by RSALDAT1 - Stairwell number one, first lift, 0 to 4 feet. Stairwell number two, first left, 0 to 4 feet. Stairwell number three, eighth left, 28 to 32 feet. Stairwell number four, ninth lift, 32 to 36 feet} ; {Activity date: 09/25/2020; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by RSALDAT1 - Partial. Stairwell number four, eighth lift, 28 to 32 feet} ; {Activity date: 09/24/2020; Status: Partial Approval; Inspector: STEVENS; Comment: Entered by JSCHNEI2 - Partial. Stairwell number four, lift number eight, 28 to 32 feet. Stairwell number three, lift number seven, 24 to 28 feet.
} ; {Activity date: 09/23/2020; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by RSALDAT1 - Partial. Stairwell number three, lift number six, 20 to 24 feet. Stairwell number four, lift number seven, 24 to 28 feet.

} ; {Activity date: 09/22/2020; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by RSALDAT1 - Partial. Stairwell number three. Fifth lift, 16 to 20 feet. Stairwell number four, sixth lift 20 to 24 feet. Elevators third floor, east and west side.} ; {Activity date: 09/21/2020; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by JSCHNEI2 - Partial. Stairwell #3, 5th lift, 16-20feet. Stairwell #4, 4th lift, 12-16 feet. Concrete block wall from B-9 to B-13.2. 1st lift, 0-4 feet.

} ; {Activity date: 09/18/2020; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by JSCHNEI2 - Partial. Level 3, Rebar between elevators.} ; {Activity date: 09/17/2020; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by RSALDAT1 - Partial. Stairwell #4, 3rd lift, 8 to 12 feet.} ; {Activity date: 09/16/2020; Status: Partial Approval; Inspector: ESTEVENS; Comment: Enter