Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date |
Description |
Inspector |
Results |
Comments |
| 09/25/2020 |
ENGINEERING - FINAL |
|
Approved |
Approved |
| 08/17/2020 |
ENGINEERING - FINAL |
|
Partial Approval |
Partially approved. OK for temporary CO, From engineering. Complete development package And sign work. |
| 08/07/2020 |
ENGINEERING - FINAL |
|
Partial Approval |
IS PARTIAL AT THIS TIME PENDING ALL OTHER INSPECTION APPROVALS, OK FOR TCO FOR STOCKING AND TRAINING ONLY, ADDITIONAL INSPECTION WILL BE REQUIRED PRIOR TO ANY OCCUPANCY OF THIS SITE. |
| 07/13/2020 |
ENGINEERING - FINAL |
|
Not ready for Inspection |
Not ready. Contractors working on trash enclosure. Terry was asked to schedule inspections from development package permit 19 Dash0183 |
| 06/23/2020 |
ENGINEERING - FINAL |
|
Not ready for Inspection |
Not ready. Trash enclosure footing is OK. Schedule inspections from development package permit. Terry with MW Morisey at 343-1700, will check to see if he has a DP. |