Inspection History Details
Inspection Status: Approved
Inspection History: BUILDING - PROGRESS
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/16/2020 | BUILDING - PROGRESS | Approved | Ap | |
| 09/11/2020 | BUILDING - PROGRESS | Partial Approval | Partial. Electric service upgrade. Site to be upgraded to 400 amp service. TEP installing new power pole and meter. TEP to energize system when pole is in place...no power kill at this time. Ok to energize when work is complete. Clearance, Code: INCR |