Inspection Status: Passed
Inspection History: COT - LCEL - Electrical Above Ceiling
| Date |
Description |
Inspector |
Results |
Comments |
| 05/26/2021 |
COT - LCEL - Electrical Above Ceiling |
JBURGE |
Approved |
Entered by VLEON1 - |
| 04/15/2021 |
COT - LCEL - Electrical Above Ceiling |
TGAUSP |
Partial Approval |
Entered by VLEON1 - Partial Approved for above ceiling in Lobby 100 and 200 |
| 02/18/2021 |
COT - LCEL - Electrical Above Ceiling |
ESTEVENS |
Partial Approval |
Entered by RSALDAT1 - Partial. Level one rooms 102 through 111. Level two room 201.
NOTE:INSPECTRO CHANGED STATUS FROM AP TO PA ASSOCIATED WITH FIELD DECISON. |
| 01/25/2021 |
COT - LCEL - Electrical Above Ceiling |
JBURGE |
Approved |
Entered by VLEON1 - Partial approval rooms 117, 136, 137, 138, 144-147, and 153, 154, 155, 157 Ok for ceiling tile |
| 01/20/2021 |
COT - LCEL - Electrical Above Ceiling |
WGALLAGHER |
Partial Approval |
Entered by RSALDAT1 - Partial approval for room 148 and 156 and plumbing wall ok to drywall and hang tiles |
| 07/23/2020 |
COT - LCEL - Electrical Above Ceiling |
DMUNIZ |
Partial Approval |
Entered by RSALDAT1 - Partial, Phase 1- Rms 171-179 ok to proceed. |
| 07/21/2020 |
COT - LCEL - Electrical Above Ceiling |
DMUNIZ |
Partial Approval |
Entered by JSCHNEI2 - Partial, Phase 1- Rms 165(A,B,C,D), 167, 168, 169, & 170 ok to Finish Acoustic ceiling’s. |