Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Passed
Inspection History: COT - LCME - Mechanical Above Ceiling
Permit Number - T20CM01086
Inspection Description - COT - LCME - Mechanical Above Ceiling
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/24/2021 | COT - LCME - Mechanical Above Ceiling | DMUNIZ | Approved | Entered by VLEON1 - |
02/18/2021 | COT - LCME - Mechanical Above Ceiling | ESTEVENS | Not ready for Inspection | Entered by RSALDAT1 - not ready. |
02/08/2021 | COT - LCME - Mechanical Above Ceiling | TTREMBULAK | Partial Approval | Entered by VLEON1 - PARTIAL ROOMS 135, 221, 202A |
02/05/2021 | COT - LCME - Mechanical Above Ceiling | WGALLAGHER | Partial Approval | Entered by VLEON1 - Partial approval for rooms 131, 131A, 136, 137, 138, 140, 141, 142, 202, 204, 205, 206, 207, 218, 218A, 219, 220, and 223 rooms checked for electrical and mechanical also ok to install ceiling tile. Note 138 has one panel cover open. Restrooms rooms 208 and 209 ok to drywall and hard lid. |
02/01/2021 | COT - LCME - Mechanical Above Ceiling | WGALLAGHER | Partial Approval | Entered by VLEON1 - Partial approval for open office rooms 222 and 201 please add seismic wires on existing air defusers, excludes area of ceiling grid removed in room 201 to access installation of 4 inch conduit for com antennas |
10/29/2020 | COT - LCME - Mechanical Above Ceiling | DMUNIZ | Partial Approval | Entered by PAHUMAD1 - Partial, Phase 3 Computer room 117 Hard duct installed, sealed and ok to insulate. |
10/26/2020 | COT - LCME - Mechanical Above Ceiling | WGALLAGHER | Partial Approval | Entered by PAHUMAD1 - Partial approval for pressure test of AVA piping for above ceiling in room 156 coil at location 1-a1 |
10/22/2020 | COT - LCME - Mechanical Above Ceiling | DMUNIZ | Partial Approval | Entered by RSALDAT1 - Partial, Duct work phase 2&3 installed and ok to proceed. |
07/23/2020 | COT - LCME - Mechanical Above Ceiling | DMUNIZ | Partial Approval | Entered by RSALDAT1 - Partial, Phase 1- Rms 171-179 ok to proceed. |
07/21/2020 | COT - LCME - Mechanical Above Ceiling | DMUNIZ | Partial Approval | Entered by JSCHNEI2 - Partial, Phase 1- Rms 165(A,B,C,D), 167, 168, 169, & 170 ok to Finish Acoustic ceiling’s. |