Permit: T20CM01086

Parcel: Unknown

Inspection Status: Passed

Inspection History: COT - LCBU - Framing

Date Description Inspector Results Comments
05/24/2021 COT - LCBU - Framing DMUNIZ Approved Entered by VLEON1 -
02/03/2021 COT - LCBU - Framing WGALLAGHER Partial Approval Entered by VLEON1 - Partial approval for restrooms #129 and 127 ok to drywall and hard lid restrooms
11/06/2020 COT - LCBU - Framing DMUNIZ Partial Approval Entered by PAHUMAD1 - Partial, Phase 3 framing for first floor ok to proceed.
10/22/2020 COT - LCBU - Framing DMUNIZ Partial Approval Entered by RSALDAT1 - Partial, Ok to Sheetrock party walls above ceiling.
07/01/2020 COT - LCBU - Framing DMUNIZ Partial Approval Entered by RSALDAT1 - Partial, Phase 1, Rm 175 framing for Hard lid ok to Sheetrock and proceed.
06/19/2020 COT - LCBU - Framing DMUNIZ Partial Approval Entered by RSALDAT1 - Partial, Phase 1- RM 176 ok to proceed.
06/15/2020 COT - LCBU - Framing DMUNIZ Partial Approval Entered by RSALDAT1 - Partial, Phase 1 interior walls ok to Sheet.
06/11/2020 COT - LCBU - Framing TTREMBULAK Partial Approval Entered by RSALDAT1 - Partial. Conference rooms 165 A-D, and hallway 175.