Permit: T20CM01086

Parcel: Unknown

Inspection Status: Passed

Inspection History: COT - LCEL - Electrical Intermediate

Date Description Inspector Results Comments
01/15/2021 COT - LCEL - Electrical Intermediate TGALLAGHER Approved Entered by VLEON1 - APPROVED, OK TO COVER
01/05/2021 COT - LCEL - Electrical Intermediate WGALLAGHER Partial Approval Entered by VLEON1 - Partial approval for rooms 135 and 136 first floor phase 3 sht 2E3.1 walls only
12/21/2020 COT - LCEL - Electrical Intermediate TTREMBULAK Partial Approval Entered by VLEON1 - Partial. OH building, rooms 218, 218A, 131, 132, and 134 in wall electric ok.
12/02/2020 COT - LCEL - Electrical Intermediate DMUNIZ Partial Approval Entered by PAHUMAD1 - Partial, Panel IT1 ok to energize.
11/19/2020 COT - LCEL - Electrical Intermediate DMUNIZ Partial Approval Entered by PAHUMAD1 - Partial, 2nd floor Conference rooms 202 & 202A Electrical in walls ok to proceed.
11/06/2020 COT - LCEL - Electrical Intermediate DMUNIZ Partial Approval Entered by PAHUMAD1 - Partial, Electrical in walls and floor boxes phase 3 first floor ok to proceed.
07/30/2020 COT - LCEL - Electrical Intermediate DMUNIZ Partial Approval Entered by RSALDAT1 - Partial, Transformer change out for TLA3 Inspected and Approved.
07/27/2020 COT - LCEL - Electrical Intermediate DMUNIZ Partial Approval Entered by RSALDAT1 - Partial, Inspection for Disconnects & Panels (LB1, LB2, LA3, LA4) ok to Energize and power check branch circuits.
07/23/2020 COT - LCEL - Electrical Intermediate DMUNIZ Partial Approval Entered by RSALDAT1 - Partial, Phase 1- Rms 171-179 ok to proceed.
07/15/2020 COT - LCEL - Electrical Intermediate DMUNIZ Partial Approval Entered by RSALDAT1 - Partial- Phase 1, Conference Rm 113 Electrical in walls approved.
06/19/2020 COT - LCEL - Electrical Intermediate DMUNIZ Partial Approval Entered by RSALDAT1 - Partial, Phase 1- RM 176 Electrical in wall ok to proceed.
06/15/2020 COT - LCEL - Electrical Intermediate DMUNIZ Partial Approval Entered by RSALDAT1 - Partial, Phase 1 Electrical in walls ok to proceed.
06/11/2020 COT - LCEL - Electrical Intermediate TTREMBULAK Partial Approval Entered by RSALDAT1 - Partial. Conference rooms 165 A-D, and hallway 175.
06/09/2020 COT - LCEL - Electrical Intermediate TTREMBULAK Cancelled Entered by RSALDAT1 - Please call your inspector for further video inspection information. No contact information given