Inspection Status: Passed
Inspection History: COT - LCEL - Electrical Underground
| Date |
Description |
Inspector |
Results |
Comments |
| 04/23/2021 |
COT - LCEL - Electrical Underground |
DQUINN |
Approved |
Entered by VLEON1 - APPROVED - north central and south central undergrounds ok to backfill for units 1-6 and 21-29 |
| 04/01/2021 |
COT - LCEL - Electrical Underground |
DQUINN |
Partial Approval |
Entered by VLEON1 - PARTIAL - 2-4” underground conduits from transformer to ct can ok to pull wire and energize. Ok to turn on distribution to north and south panels. North central and south central panels nr.
|
| 03/12/2021 |
COT - LCEL - Electrical Underground |
IVR USER |
Cancelled |
Entered by IVR USER - IVRS - RI canceled |
| 12/22/2020 |
COT - LCEL - Electrical Underground |
DMUNIZ |
Partial Approval |
Entered by RSALDAT1 - Partial, Direct burial cables installed from Pedestals 1-10 ok to shade, Caution tape, and backfill. |
| 12/21/2020 |
COT - LCEL - Electrical Underground |
DMUNIZ |
Partial Approval |
Entered by VLEON1 - Partial, Trenches ok to lay direct burial conductors for Pedestals. |