Permit: T20CM00826

Parcel: 117200270


Addresses:

260 S CHURCH AV


Inspection Status: Approved

Inspection History: BUILDING PRE-SLAB

Permit Number - T20CM00826

Inspection Description - BUILDING PRE-SLAB

Inspection Status - Approved

Date Description Inspector Results Comments
10/27/2020 BUILDING PRE-SLAB Approved
09/09/2020 BUILDING PRE-SLAB Partial Approval Partial. Level 1; Southwest corner section. Ok to place concrete in progress area.
09/09/2020 BUILDING PRE-SLAB Partial Approval Partial. Level 1; Southwest corner section. Ok to place concrete in progress area.
09/04/2020 BUILDING PRE-SLAB Partial Approval Partial. Level #1; Southeast section. Ok to place concrete in progress area.
09/02/2020 BUILDING PRE-SLAB Partial Approval Partial. Ramp slab at Level 1.5; GL: 2-5/A-B. Ok to place concrete in progress areas.
08/27/2020 BUILDING PRE-SLAB Partial Approval Partial. South stairwell at Levels #1-3; stair landings; Elevator slabs at Levels #1-4. Ok to place concrete in progress areas.
08/18/2020 BUILDING PRE-SLAB Partial Approval Partial. Level #1; Northeast section. Ok to place concrete. (No electric in this slab)
08/14/2020 BUILDING PRE-SLAB Partial Approval Partial. Level #2 Northeast section. Ok to place concrete in progress area.
08/13/2020 BUILDING PRE-SLAB Partial Approval Partial. Parking garage level 2 southwest corner.
08/11/2020 BUILDING PRE-SLAB Partial Approval Partial. Level #2 Southeast portion slab. Ok to place concrete in progress areas.
08/07/2020 BUILDING PRE-SLAB Partial Approval Partial. Level #3 to Level 2.5 (Northeast sector). Ok to place concrete in progress area.
08/06/2020 BUILDING PRE-SLAB Partial Approval Partial. Level #3; Northwest section. Ok to place concrete in progress areas.
08/05/2020 BUILDING PRE-SLAB Partial Approval Partial. Level #3; Slab at South portion of Level #3.
07/30/2020 BUILDING PRE-SLAB Partial Approval Partial. Level 3.5-3 Northeast section
07/28/2020 BUILDING PRE-SLAB Partial Approval
07/24/2020 BUILDING PRE-SLAB Partial Approval Partial. Level #4; Southeast section. Ok to place concrete in progress areas.
07/23/2020 BUILDING PRE-SLAB Not ready for Inspection Not ready. Contractor cancelled; rained out