Inspection History Details
Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
Permit Number - T20CM00546
Inspection Description - ENGINEERING - FINAL
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/15/2021 | ENGINEERING - FINAL | Approved | ||
| 12/28/2020 | ENGINEERING - FINAL | Partial Approval | IS PARTIAL AT THIS TIME, OK FOR A TCO BUTNOT FOR THE FINAL. 1) COMPLETE THE SITE AS SHOWN ON THE APPROVED PLANS OR PROVIDE US WITH APPROVED REVISED DRAWINGS FOR ALL CHANGES TO THIS SITE. A 1 STORY OFFICE STRUCTURE IS NOTED ON THE APPROVED PLANS. 2) REPAIR THE DAMAGED HANDICAP ACCESS RAMPS ON LITTLE TOWN ROAD AS NEEDED BY THE CITY OF TUCSON TRANSPORTATION DEPARTMENT. 3) REMOVE THE STOCKPILE OF MATERIAL ON THE EAST SIDE OF THIS SITE. 4) HYDROSEED ALL DISTURBED AREAS ADJACENT TO THIS SITE, ON ALL 4 SIDES. | |
| 12/10/2020 | ENGINEERING - FINAL | Partial Approval | PARTIAL AT THIS TIME, OK FOR A TCO. FINAL WILL NOT BE GIVEN TILL ALL OF THE WORK HAS BEEN COMPLETED AND VERIFIED BY THE INSPECTOR. | |
| 12/09/2020 | ENGINEERING - FINAL | Denied | Denied. Development package permit has not yet been approved. Stand with venture west at 465-9087 | |
| 12/07/2020 | ENGINEERING - FINAL | Partial Approval | PARTIAL PENDING THE CLOSURE OF THE DEVELOPMENT PACKAGE | |
| 11/25/2020 | ENGINEERING - FINAL | Not ready for Inspection | Not ready. General contractor brought letter for trash enclosureAnd water harvesting.From engineer of record. | |
| 05/12/2020 | ENGINEERING - FINAL | Not ready for Inspection | Not ready |