Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/02/2021 | EXCAVATION/LAYOUT REBAR & ZON | Approved | Approved | |
01/29/2021 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Retaining wall footing at Northeast section (approximately 165 ‘). Ok to place concrete in footings. | |
12/07/2020 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | Not ready. Contractor cancelled. Will reschedule for 8 December. | |
11/17/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Columns at gridlines 6B and 6B.5. Block wall, Gridlines GF-G7 to G9, 2nd lift top out. Footing inspection at gridlines GF-G5. | |
11/13/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Rebar pad at elevator and stairwell, Gridlines GF-G6. | |
11/10/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Elevator and stairwell pad at gridlines GF-G6. | |
10/27/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. West side retaining wall, Gridlines G1-GE to E. Footing, gridlines G3-E to F. | |
10/22/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Level #1; Section: Sea Hawks at Gl: A/2-6; step down footing. Ok to place concrete in progress area. This inspection was performed on 17 October on an after hours inspection as part of inspection for T20CM00313. No additional charges for this inspection. |
|
10/22/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Footing for parking deck. Ramp wall and column on east side of elevator. | |
09/14/2020 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | Not ready, not complete. | |
09/10/2020 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | Canceled by contractor. | |
09/03/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Three sections of Retaining wall at G1-GE and G2-GF. | |
08/27/2020 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | Canceled by contractor | |
08/19/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Inspection completed on 18 August. | |
08/18/2020 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | Not ready. Contractor cancelled will reschedule for 19 August. | |
08/14/2020 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | Not ready. Contractor cancelled. | |
08/13/2020 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | Canceled by contractor. | |
08/12/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. North side stairwell at parking garage, and footing at gridline G2 to G5. | |
08/11/2020 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | Not ready, not complete. | |
08/07/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial rebar and stem wall at stairwell location G5-GA. | |
08/06/2020 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | Not ready, not complete. | |
08/05/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Footing for the stairwell at GA-G5. | |
08/03/2020 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | . Not ready. Contractor cancelled. Will reschedule for 4 August. | |
07/31/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Building #4 continuous footing at GL: G-F/G6; G9/GC 4' x 18"; 2' x 18" | |
07/30/2020 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | Canceled by contractor. | |
07/29/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. From GB-G10 to GA-G10 to GA-G10 thru G6. | |
07/27/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | West side footing from GE-G1 to GB-G1 to GB-G2 to GA-G2 to GA-G4 | |
07/24/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Columns at G10-GC, G10-GD, G10-GE. | |
07/22/2020 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | Canceled by contractor | |
07/21/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Columns at GB-G10, GC-G9, GE-G2, GF-G2, GF-G3, GF-G4, GF-G5. | |
07/20/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Columns at G9-GA, G9-GB, G9-GD, G9-GE, G9-GF, G8-GC, G8-GD, G8-GF, G6-GC, G6-GD, G5-GC, G5-GD. Elevator rebar A-G5 to G6. Footings at G10-GC, G10,GD, G10-GE, G2-GE, GF-G2, GF-G3, GF-G4, GF-G5. Elevator at A-G5 to G6. |
|
07/17/2020 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | Cancel | |
07/16/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Footings at GC-G5, GC-G6, GC-G8, GD-G5, GD-G6, GD-G8, GD-G9. | |
07/15/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Partial. Columns at G2-GA, G2-GB. | |
07/14/2020 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | . Partial. Footings at G2-GA, G2-GB. |