Permit: T20CM00314

Parcel: 12513068A

Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Permit Number - T20CM00314

Inspection Description - EXCAVATION/LAYOUT REBAR & ZON

Inspection Status - Approved

Date Description Inspector Results Comments
11/02/2021 EXCAVATION/LAYOUT REBAR & ZON Approved Approved
01/29/2021 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Retaining wall footing at Northeast section (approximately 165 ‘). Ok to place concrete in footings.
12/07/2020 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection Not ready. Contractor cancelled. Will reschedule for 8 December.
11/17/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Columns at gridlines 6B and 6B.5. Block wall, Gridlines GF-G7 to G9, 2nd lift top out. Footing inspection at gridlines GF-G5.
11/13/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Rebar pad at elevator and stairwell, Gridlines GF-G6.
11/10/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Elevator and stairwell pad at gridlines GF-G6.
10/27/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. West side retaining wall, Gridlines G1-GE to E. Footing, gridlines G3-E to F.
10/22/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Level #1; Section: Sea Hawks at Gl: A/2-6; step down footing. Ok to place concrete in progress area.
This inspection was performed on 17 October on an after hours inspection as part of inspection for T20CM00313. No additional charges for this inspection.
10/22/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Footing for parking deck. Ramp wall and column on east side of elevator.
09/14/2020 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection Not ready, not complete.
09/10/2020 EXCAVATION/LAYOUT REBAR & ZON Cancelled Canceled by contractor.
09/03/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Three sections of Retaining wall at G1-GE and G2-GF.
08/27/2020 EXCAVATION/LAYOUT REBAR & ZON Cancelled Canceled by contractor
08/19/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Inspection completed on 18 August.
08/18/2020 EXCAVATION/LAYOUT REBAR & ZON Cancelled Not ready. Contractor cancelled will reschedule for 19 August.
08/14/2020 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection Not ready. Contractor cancelled.
08/13/2020 EXCAVATION/LAYOUT REBAR & ZON Cancelled Canceled by contractor.
08/12/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. North side stairwell at parking garage, and footing at gridline G2 to G5.
08/11/2020 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection Not ready, not complete.
08/07/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial rebar and stem wall at stairwell location G5-GA.
08/06/2020 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection Not ready, not complete.
08/05/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Footing for the stairwell at GA-G5.
08/03/2020 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection . Not ready. Contractor cancelled. Will reschedule for 4 August.
07/31/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Building #4 continuous footing at GL: G-F/G6; G9/GC 4' x 18"; 2' x 18"
07/30/2020 EXCAVATION/LAYOUT REBAR & ZON Cancelled Canceled by contractor.
07/29/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. From GB-G10 to GA-G10 to GA-G10 thru G6.
07/27/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval West side footing from GE-G1 to GB-G1 to GB-G2 to GA-G2 to GA-G4
07/24/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Columns at G10-GC, G10-GD, G10-GE.
07/22/2020 EXCAVATION/LAYOUT REBAR & ZON Cancelled Canceled by contractor
07/21/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Columns at GB-G10, GC-G9, GE-G2, GF-G2, GF-G3, GF-G4, GF-G5.
07/20/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Columns at G9-GA, G9-GB, G9-GD, G9-GE, G9-GF, G8-GC, G8-GD, G8-GF, G6-GC, G6-GD, G5-GC, G5-GD. Elevator rebar A-G5 to G6.

Footings at G10-GC, G10,GD, G10-GE, G2-GE, GF-G2, GF-G3, GF-G4, GF-G5.

Elevator at A-G5 to G6.
07/17/2020 EXCAVATION/LAYOUT REBAR & ZON Cancelled Cancel
07/16/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Footings at GC-G5, GC-G6, GC-G8, GD-G5, GD-G6, GD-G8, GD-G9.
07/15/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Partial. Columns at G2-GA, G2-GB.
07/14/2020 EXCAVATION/LAYOUT REBAR & ZON Partial Approval . Partial. Footings at G2-GA, G2-GB.