Inspection Status: Continued
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 12/11/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Pouring Scupper apron on North side of Seneca. |
| 01/17/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Final. No Issues. |
| 01/17/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
|
| 12/06/2019 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Precon with Hunter. Work in ROW to start 12/9. 2 Type 2 Scuppers with aprons. Class S 3000psi concrete. |