Inspection History Details
Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/13/2020 | TDOT-EXCAV GENERAL INSPECTION | Approved | new MH installed and backfilled with slirry, 8 in sewer line installed to property. Trench also backfilled with slurry. New asphalt repair complete and area has a new concrete collar. No issues or repairs needed | |
| 03/06/2020 | TDOT-EXCAV GENERAL INSPECTION | Continued | MH base poured on3/4/20 all arial work complete and new pole in place. Old pole has been removed. No issues or repairs needed |
|
| 02/20/2020 | TDOT-EXCAV GENERAL INSPECTION | Continued | -Precon on site a.Notify city irrigation b.TDOT asphalt Mix c.repair striping d.Slurry backfill e. Recess plates f. verified no moritorium, work on Drexel |