Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T19RW07220

Parcel: Unknown


Addresses:

8024 E 7TH ST


Inspection Status: Re-inspection required

Inspection History: TRSP - ROW - Recurring

Permit Number - T19RW07220

Inspection Description - TRSP - ROW - Recurring

Inspection Status - Re-inspection required

Date Description Inspector Results Comments
09/03/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. No activity on site by either contractor or subcontractor. Door hangers have been sent out.
09/15/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
09/02/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. Pre-Con taking place yesterday date Wednesday, September 1. TE people were receiving electric from has been moved to another pole per TEP Louis. Valor to send out notices and send a copy of notice sent out and addresses that were sent to.
09/14/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
08/02/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. Work being performed on fiber not pole.
09/13/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
07/29/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. Permit has been renewed still no work on site
09/09/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Continued. No traffic control plan in place.
01/18/2022 TRSP - ROW - Recurring Passed TDOT-EXCAV GENERAL INSPECTION - All work complete, no concerns
11/19/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Pole has been installed. No power to 5G Pole yet.
07/26/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued No signs of work yet
09/07/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Continued. No traffic control plan in place. Work has not yet begun.
11/17/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. No activity on site by either contractor or subcontractors. Quail barricade yesterday came and removed cold patch in three locations. Installed hot patch and will be closing out on this site.
11/16/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. No activity on site by either contractor or subcontractors. Patchwork from boring pets need to be addressed.
11/15/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. No activity on site by the contractor or subcontractor. Asphalt patches in Rodeway still need to be addressed.
11/12/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. No activity on site for either contractor or subcontractors.
01/18/2022 TRSP - ROW - Recurring Passed TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site.
11/10/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. No activity on site by the contractor or subcontractors. Asphalt patching were boring pets took place need to be addressed.
11/05/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. No activity on site by either contractor or subcontractor.
11/17/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site.
11/04/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. Asphalt patch work needs to be complete. No activity on site by either contractor or subcontractors.
11/15/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site.
11/03/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. No activity on site by either contractor or subcontractor. I had a field meeting with Velex yesterday on site to determine asphalt patches that need to be complete.
11/12/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site.
11/02/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. On-site meeting with Velllex. To determine what I need to be done to complete my punchlist. Will be removing and re-patching receiving pits from boring. To be using hot mix with tech oil.
11/10/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site.
11/01/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. No activity on site by the contractor or subcontractors.
11/05/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site.
03/17/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Not Ready for Inspection. No sign of work. No blue stake. No layout.
09/03/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Continued. No traffic control plan in place.
10/29/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. No activity on site by the contractor or subcontractor.
11/04/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site.
10/28/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - .Continued. No activity on site with a contractor or subcontractors.
11/03/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site.
10/26/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. No activity on site by the contractor or subcontractor.
11/02/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site.
10/25/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. No activity by the contractors or subcontractors.
11/01/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site.
10/22/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. No activity on site by the contractor or subcontractors.
10/29/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site.
10/21/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. No activity on site by the contractor or subcontractors.
10/28/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site.
10/20/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. No activity on site by the contractor or subcontractor. Patchwork needs to be addressed on south west corner of the intersection.
10/26/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site.
10/18/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. No activity on site by the contractor or subcontractors.
10/25/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site.
10/18/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. No activity on site by the contractor or subcontractors. Patch on seven needs to be replaced with hot patch and Tac oil.
10/22/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site.
10/15/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. Vertical one on site working on antenna.
10/21/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site.
05/20/2020 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - No sign of work. No bluestake. Site marked.
09/02/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Continued. Construction on site has not yet begun. No traffic elements in place.
10/14/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. No activity on site. Patchwork needs to be removed and reinstal led with hot patch and tack oil at intersection.
10/20/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site.
10/13/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. No activity on site by the contractor or subcontractor. Patchwork on seventh Street needs to be addressed. Cold patch needs to be removed and hot patch with tech will need to be installed.
10/18/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site.
10/12/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. No activity on site by the contractor or subcontractor. Asphalt patches seem to be taken care of. Asphalt patches on seventh still need to be addressed.
10/18/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Continued
10/11/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. No activity on site by the contractors subcontractors.
10/15/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site.
10/07/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. No activity on site by their contractor or subcontractors.
10/14/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site.
10/06/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. No activity on site by the contractor or subcontractors.
10/13/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site.
10/05/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. No activity on site by the contractor or subcontractor. Asphalt were boring location. receiving pits are located need to be re-asphalted.
10/12/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site.
10/04/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. No activity on site by the contractors or subcontractors.
10/11/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site.
10/01/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. No activity on site by the contractor or subcontractor.
10/07/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site.
09/27/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. . Subcontractor vertical one on site pressure washing and general cleanup.
10/06/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site.
03/11/2020 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - No bluestake. No sign of work. No layout. Location marked.
03/24/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Not Ready for Inspection. Sign of work. No blue staking.
09/24/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. No activity on site by the contractor or subcontractors.
10/05/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Continued. No activity on site. No traffic control plan in place.
09/23/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. Vertical one on site pouring a pool foundation.
10/04/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Continued. No activity on site. No traffic elements in place.
09/22/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. Vertical one on site installing sono tube and Pole cage.
10/01/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Continued. No activity on site. No traffic control plan in place.
09/21/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued.
09/27/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
09/20/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. No activity on site by the contractor or subcontractor.
09/24/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Continued. No activity on site. No traffic control plan in place.
09/16/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. Subcontractor on site boring. The same contractor has a open transfer receiving pit on south east corner of seventh
09/23/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
09/14/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. No activity on site by either contractor or subcontractors.
09/22/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
09/13/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. Traffic control plan in place. No activity inside.
09/21/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Continued. No activity on site. No traffic control plan in place.
09/09/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. No work has started yet by either contractor or subcontractor.
09/20/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Continued. No activity on site. Traffic control elements are all stage on side of road.
09/07/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Continued. No activity on site.
09/16/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control is set according to plan.
01/23/2020 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - No sign of work. No layout. No bluestake.
03/17/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Not Ready for Inspection. No sign of work. No blue stake. No layout.