Inspection Status: Closed
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 03/26/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Closed |
Closed. Will try to contact owner of cable. Sent email with photos to Lance. |
| 03/11/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Cable in asphalt not removed. |
| 02/28/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Work not corrected. Called Bear Communication. |
| 01/31/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Roadway not repaired. Permit expired. |
| 01/22/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Roadway not repaired. Tried calling Bear Communications but no answer. |
| 01/22/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Travel to Bear Communications office to get a working office phone number. Discussed 3 projects that needs roadway repair before they can be closed out with Jason Knight 520-329-0785 These prmits are: T19RW06271, T19RW06272, T19RW06065. |
| 01/10/2020 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Old cable still in asphalt. Called main office and left message. |
| 12/03/2019 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Old cable still in roadway. Called main office to find out when job will be completed.No info given will call back. |
| 11/20/2019 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
No change, permit expired, old cable is still in place (cable was layed within the 1" asphalt in roadway and over time the asphalt wore away and cable is exposed |
| 10/31/2019 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
No change. |
| 10/21/2019 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
No change. Called contractor about abondoned cable in asphalt surface. |
| 10/01/2019 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Boring completed, pedistal installed. Old cable still in roadway surface and needs to be removed. |
| 09/12/2019 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Contractor requested a precon at 10 am. Will start on 09/13. Will remove exposed cable in roadway and patch roadway. |