Inspection Status: Continued
Inspection History: TDOT-EXCAV GENERAL INSPECTION
Permit Number - T19RW04297
Inspection Description - TDOT-EXCAV GENERAL INSPECTION
Inspection Status - Continued
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/05/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Valve box concrete collars completed. | |
09/05/2019 | TDOT-EXCAV GENERAL INSPECTION | Approved | Completed. Concrete collars at valve boxes completed. | |
08/23/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | East bound lanes - remove cold patch, compact and test, place asphalt in 2 lifts. With barricades. | |
08/22/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | West bound lanes - remove cold patch, compact and test, place asphalt in 2 lifts. With barricades. | |
08/21/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Pressure testing pipes under roiadway. Working on cold patches. | |
08/20/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Repaired cold patch. Roadway repair starts 8/22 | |
08/15/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Placed 2 pipe crossings in Ft. Lowell, cold patch roadway. Heat making patches soft and are repairing them. Told contractor must place asphalt ASAP. | |
08/09/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Pot hols at crossings with cold patch. | |
08/06/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Precon at 9am. 2 water crossings in Fort Lowell Rd. Recessed plates required or cold patch till asphalt is placed. ABC backfill or slurry mix. |