Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T19RW04068

Parcel: Unknown


Addresses:

4253 E LESTER ST


Inspection Status: Re-inspection required

Inspection History: TRSP - ROW - Recurring

Permit Number - T19RW04068

Inspection Description - TRSP - ROW - Recurring

Inspection Status - Re-inspection required

Date Description Inspector Results Comments
10/06/2020 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Met with Noah Hadley, new foreman for Velex. Discussed need for resident notification of pending work to adjacent property to be 5 working days per precon. Directed contractor to assure that all barricades used and signage overnight have lights installed per COT MUTCD requirements. Assured that contractor would abide by work hours of 700a to 300p per permit requirements. Contractor told to maintain housekeeping and keep pedestrian paths clear of debris.
10/03/2020 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Saturday visit to inspect weekend housekeeping. No critical concerns. Hand graded some ROW area adjacent to the excavation fencing for the pole. Drove neighborhood and did not observe any work.
09/17/2020 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - No change.
09/14/2020 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - No change.
09/03/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Traffic control devices have been removed from site.
09/09/2020 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - New footing placed. New pole set without light or equipment. Barricades on shoulder. No sidewalk in area. Roadway not affected.
02/01/2021 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - All construction completed. Permit open so that contractor can calibrate and adjust the electronics.
08/10/2020 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Removed the "CLS" status so that this permit may stay open, not FINAL.
06/22/2020 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - No bluestake. No sign of work. No layout.
12/14/2020 TRSP - ROW - Recurring Passed TDOT-Routine Barricade Inspect - Approved
01/21/2020 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - No sign of work. No bluestake, no layout.
10/09/2020 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Continued
09/03/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Att pole. Landscaping restored. Pole placed and sign placed. Site passes ROW inspection.
02/01/2021 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Dirt shoulder cleaned up. Sidewalk undisturbed.
12/14/2020 TRSP - ROW - Recurring Passed TDOT-EXCAV GENERAL INSPECTION - New pole installed. All boxes set. All work performed in dirt shoulder. Roadway and sidewalk not affected. Power conduit installed two pole. Site cleaned up. Permit closed.
10/09/2020 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - Crew pulling wire at New pole.
10/03/2020 TRSP - ROW - Recurring Re-inspection required TDOT-Routine Barricade Inspect - Drove area. Moved some non used barricades out of the path of pedestrian travel adjacent to the pole fencing. Will address issues with contractor on Monday.
10/07/2019 TRSP - ROW - Recurring Re-inspection required TDOT-EXCAV GENERAL INSPECTION - No sign of work, no bluestake, no layout.