Inspection History Details
Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
Permit Number - T19RW03822
Inspection Description - TDOT-EXCAV GENERAL INSPECTION
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/06/2020 | TDOT-EXCAV GENERAL INSPECTION | Approved | all gas lines have been installed and all backfill has been slurry. All asphalt patches and concrete repairs have been completed. SW gas had a full time inspector on site for all gas lines. Backfill was not a issue due toslurry. and all repairs have been excepted. Longline gas project has finally been completed | |
| 08/23/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | 1000 LF of 12 in main installed on 20th, Fugal working late to install pipe. $th had to be closed due to the length of pipe and it was better for the bus route to close for one day only. Fugal started to perm patch excavations All excavations have been slurried per COT request. No issues at this moment |
|
| 08/08/2019 | TDOT-EXCAV GENERAL INSPECTION | Approved | 7/12/19 precon 7/15/19-7/19 potholing and mobilization 7/22-7/26 welding 12 in main 8/1/-8/9 lots of work in area--welding main and boring and installing new main, potholing areas. Contractor is in communication for all closures and issues. No complaints and no issues as of yet |