Inspection Status: Continued
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 10/07/2019 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Met with John from Optimum concrete checked grade and forms. Made some adjustments to forms at tie in of sidewalk to Habitat for humanity, and at wing on east end of project. Pour scheduled for 9am today. Will return for final when kittle calls off barricades and backfill is complete. |
| 07/09/2019 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
Precon 7/9 with Kittle Design and Arcadia Landscape and Optimum Concrete. Starting week of 7/15. |