Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Passed
Inspection History: TRSP - ROW - Recurring
Permit Number - T19RW02913
Inspection Description - TRSP - ROW - Recurring
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/31/2022 | TRSP - ROW - Recurring | Passed | TDOT-EXCAV GENERAL INSPECTION - Mast arm and light placed. Landscaping and sidewalk have been restored. Rejected concrete was replaced ROW PASSES final inspection. | |
01/04/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Pole placed by vertical one. Concrete over 1/4” kickers to existing and sunk on edges. Concrete around box not replaced. Concrete sidewalk is in reject and needs repair for sunken areas. | |
01/31/2022 | TRSP - ROW - Recurring | Passed | TDOT-Routine Barricade Inspect - Traffic control devices have been removed. | |
10/27/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Vertical one poured concrete and slurry for site. Will open sidewalk and clean up. Gave permission to work until 1630-1700. Concrete orders were only available for afternoon pour so clean up will need to be longer. Traffic control showed up late for pickup. Traffic control is being picked up now. Spoke to frank at Quail barricades and asked to please have traffic control removed BY 1530. | |
01/04/2022 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Traffic control devices removed from roadway, staged for set up/pickup. | |
10/27/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Vertical one and wolverine trucking on site and beginning work. | |
10/26/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Vertical one removed pole and side walk panels. Breaking caisson to 36” below subgrade. Panels need to be filled and cold patch placed for pedestrians over night. | |
10/27/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Traffic control is set according to plan. Quail late for pickup. | |
10/21/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-EXCAV GENERAL INSPECTION - Pre construction meeting with velex and vertical one. Remove pole and caisson from sidewalk and place a swf pole with light in landscaping. Tom Adkins gave approval for wing of ada ramp to be replaced without doing ramp restoration. Bus stop to be moved and notified. Shared power site. Communications from crown castle onsite. Trafficade to remove sign on pole by end of week or before construction begins. | |
10/27/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Traffic control devices removed from roadway, staged for set up/pickup. | |
08/07/2020 | TRSP - ROW - Recurring | Passed | TDOT-EXCAV GENERAL INSPECTION - Facility complete. Final. | |
10/26/2021 | TRSP - ROW - Recurring | Re-inspection required | TDOT-Routine Barricade Inspect - Traffic control is set according to plan. |